Question

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:

  Direct materials: 4 kg at $8.00 per kg $ 32.00  
  Direct labour: 2 hours at $16 per hour 32.00  
  Variable overhead: 2 hours at $6 per hour 12.00  
  Total standard cost per unit $ 76.00  

The company planned to produce and sell 32,000 units in March. However, during March the company actually produced and sold 37,000 units and incurred the following costs:

  1. Purchased 160,000 kg of raw materials at a cost of $7.40 per kg. All of this material was used in production.
  2. Direct labour: 67,000 hours at a rate of $17 per hour.
  3. Total variable manufacturing overhead for the month was $422,100.

1.what is the material price variance for march (  (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

2. What is the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

3. what is the labour rate variance for March?(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

4. what is labour efficiency varience for march?

5. what is the variable overhead spending variance for march?

6. what is the variable overhead rate variance for march?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1.

Material price variance for march = (Standard rate - Actual rate) * Actual quantity of raw materials used.

($8.00 - $7.40) * 160,000 kg = $96,000 F.

Answer 2.

Materials quantity variance for March = (Standard quantity for Actual production - Actual quantity of raw materials used) * Standard rate

Where, Standard quantity for Actual production = Actually quantity produced * Standard raw material per unit

= [(37,000 units * 4 kg) - 160,000 kg] * $8.00

= (148,000 kg - 160,000 kg) * $8.00  

= $96,000 U.

Answer 3.

Labour rate variance for March = (Standard rate - Actual rate) * Actual hours worked

= ($16 - $17) * 67,000 hours

= $67,000 U.

Answer 4.

Labour efficiency variance for march = (Standard hours for Actual production - Actual hours worked) * Standard rate

Where, Standard hours for Actual production = Actually quantity produced * Standard hours material per unit

= [(37,000 units * 2 hour) - 67,000 hours] * $16

= (74,000 hours - 67,000 hours) * $16

= $112,000 F.

Answer 5.

Variable overhead spending variance = Standard variable manufacturing overhead Actual production -  Actual variable manufacturing overhead

Where = Standard variable manufacturing overhead Actual production = Actually quantity produced *  Standard hours * Standard rate

= (37,000 units * 2 hour * $6) - $422,100

= $444,000 -  $422,100

= $21,900 F.

Answer 6.

Variable overhead rate variance for march = (Standard rate of Variable overhead  * Actual hours worked) - Actual variable manufacturing overhead

= ($6 per hour * 67,000 hours ) - $422,100

= $402,000 - $422,100

= $20,100 U.

Add a comment
Know the answer?
Add Answer to:
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $8.00 per kg $ 40.00     Direct labour: 4 hours at $15 per hour 60.00     Variable overhead: 4 hours at $5 per hour 20.00     Total standard cost per unit $ 120.00   The company planned to produce and sell 21,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $10.00 per kg $ 50.00     Direct labour: 3 hours at $14 per hour 42.00     Variable overhead: 3 hours at $4 per hour 12.00     Total standard cost per unit $ 104.00   The company planned to produce and sell 29,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 4 kg at $9.00 per kg $ 36.00     Direct labour: 3 hours at $12 per hour 36.00     Variable overhead: 3 hours at $8 per hour 24.00     Total standard cost per unit $ 96.00   The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT