Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:
Direct materials: 5 kg at $8.00 per kg | $ | 40.00 |
Direct labour: 4 hours at $15 per hour | 60.00 | |
Variable overhead: 4 hours at $5 per hour | 20.00 | |
Total standard cost per unit | $ | 120.00 |
The company planned to produce and sell 21,000 units in March. However, during March the company actually produced and sold 24,000 units and incurred the following costs:
1. What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)
2. What is the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)
5. What is the labour rate variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)
6. What is the labour efficiency variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)
7. What is the variable overhead spending variance for March? (Do not round intermediate calculations. Round the actual overhead rate to two decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)
8. What is the variable overhead rate variance for March? (Round the actual overhead rate to two decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)
1) material price variance = (8-6.4)*150000 = 240000 F
2) Material quantity variance = (24000*5-150000)*8 = 240000 U
5) Labor rate variance = (15-18)*66000 = 198000 U
6) Labor efficiency variance = (24000*4-66000)*15 = 450000 F
7) Variable overhead spending variance = (24000*20-413280) = 66720 F
8) Variable overhead rate variance = (5*66000-413280) = 83280 U
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $10.00 per kg $ 50.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $4 per hour 12.00 Total standard cost per unit $ 104.00 The company planned to produce and sell 29,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $8.00 per kg $ 32.00 Direct labour: 2 hours at $16 per hour 32.00 Variable overhead: 2 hours at $6 per hour 12.00 Total standard cost per unit $ 76.00 The company planned to produce and sell 32,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...