1: A project has proposed investment is (Year 0 ) 320K, (Year 1) 150K, 100K, 60K, 0, 0, and (Year 6) 25K over these years respectively. The income is 0,0,200K, 225K, 250K, 175K, and 125K over these same corresponding years. Use this same data for Questions 25-28. The required rate of return is 14%. What is the Net inflow in Year 3? 175K 60K 225K 165K
2:
The required rate of return is 14%. What is the present value of Year 6 net inflow?
|
|||
|
|||
|
|||
|
3:
The required rate of return is 14%. What is the net present value of the project?
|
|||
|
|||
|
|||
|
4: At what rate of return is the NPV approximately zero?
|
|||
|
|||
|
|||
|
Given,
Year | Investments, Cash outflow | Profit, Cash inflow |
n | A | B |
0 | 320000 | 0 |
1 | 150000 | 0 |
2 | 100000 | 200000 |
3 | 60000 | 225000 |
4 | 0 | 250000 |
5 | 0 | 175000 |
6 | 25000 | 125000 |
Note: Investments are cash outflows
Profits are Cash inflows.
(a) 225K
Net flow for third year = Cash inflow(Year 3) - Cash Outflow(Year 3 = 225,000 - 0 = 225,000
(b) 45.5K
We know that
NPV = F / [ (1 + i)^n ]
NPV = Net present value
F = Future Cash flow
i = discount rate
n = number of years
For the Year 6, Future cash flow, F = Net Cash flow = Cash Inflow(Year 6) - Cash Outflow(Year 6) = 125,000 - 25,000 = 100,000
i = 14%
n = 6 years
Hence by using the formula mentioned above the required NPV of netflow for year 6 = 100,000 /[1+14/100]^6 = 45,558.65
(c) 21.2K
For calculating the NPV of the total project we need to calculate the net present value of the cash flow of each year as we did for year 6. The calculation and the tabulation are as shown below:
Year | Investments,Cash outflow | Profit, Cash inflow | Net Cash flow | Net present value |
n | A | B | F = B-A | NPV = F / [ (1 + i)^n ] |
0 | 320000 | 0 | -320000 | -320000.00 |
1 | 150000 | 0 | -150000 | -131578.95 |
2 | 100000 | 200000 | 100000 | 76946.75 |
3 | 60000 | 225000 | 165000 | 111370.30 |
4 | 0 | 250000 | 250000 | 148020.07 |
5 | 0 | 175000 | 175000 | 90889.52 |
6 | 25000 | 125000 | 100000 | 45558.65 |
Net present value of project = | 21206.35 |
The net present value of the project is equal to the sum of the net present value of the project for all the years, which is calculated in the table above and equal to 293,358.7Please follow the notations for clear understanding.
(d) 15.5%
By calculating the NPV for all the above-mentioned interest rate as below in the table:
Year | Investments,Cash outflow | Profit, Cash inflow | Net Cash flow | Net present value @ 14% | Net present value @ 17.2% | Net present value @ 15.5% | Net present value @ 10.7% |
n | A | B | F = B-A | NPV = F / [ (1 + i)^n ] | NPV = F / [ (1 + i)^n ] | NPV = F / [ (1 + i)^n ] | NPV = F / [ (1 + i)^n ] |
0 | 320000 | 0 | -320000 | -320000.00 | -320000.00 | -320000.00 | -320000.00 |
1 | 150000 | 0 | -150000 | -131578.95 | -127986.35 | -129870.13 | -135501.36 |
2 | 100000 | 200000 | 100000 | 76946.75 | 72802.25 | 74961.11 | 81602.74 |
3 | 60000 | 225000 | 165000 | 111370.30 | 102494.63 | 107087.31 | 121630.10 |
4 | 0 | 250000 | 250000 | 148020.07 | 132504.17 | 140479.22 | 166475.19 |
5 | 0 | 175000 | 175000 | 90889.52 | 79140.72 | 85138.92 | 105268.87 |
6 | 25000 | 125000 | 100000 | 45558.65 | 38586.41 | 42121.91 | 54339.33 |
Net present value of project = | 21206.35 | -22458.17 | -81.66 | 73814.88 |
Clearly for the interest rate 15,5% NPV of the project is closer to zero.
1: A project has proposed investment is (Year 0 ) 320K, (Year 1) 150K, 100K, 60K,...
A potential project requires an initial investment of $75,000 at the beginning of the 1st year, and will give a net cash inflow of $25,000 per year (realized at the end of the 1st, 2nd and 3rd year respectively) for three years. The required rate of return is 15%. What is the Net Present Value? NPV = Ao + Sum from t=0 to t=n of Ft /(1+R)t
Calculate the net present value for a 15-year project with an initial investment of $ 0 and a cash inflow of $2,000 per year. Assume that the firm has an opportunity cost of 13%. Comment on the acceptability of the project. The project's net present value is $____ .
Suppose a company has proposed a new 5-year project. The project has an initial outlay of $228,000 and has expected cash flows of $30,000 in year 1, $46,000 in year 2, $51,000 in year 3, $64,000 in year 4, and $76,000 in year 5. The required rate of return is 17% for projects at this company. What is the net present value for this project? (Answer to the nearest dollar.)
A project has the following cash flows: Year Cash Flow 0 $ 66,500 1 –41,000 2 –32,800 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return % What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
20) Assume a proposed project under consideration by the James River Co. requires $28,900 in fixed assets. The firm plans to ignore bonus depreciation and instead apply straight-line depreciation to zero over the asset's 6-year life. An aftertax salvage value of $5,400 is expected. The project will produce an annual operating cash flow of $7,300 and will require net working capital of $500 initially plus an additional $500 in Year 3. Net working capital will be restored to its original...
A project will produce cash inflows of $3,100 a year for 3 years with a final cash inflow of $4,400 in year 4. The project's initial cost is $10,400. What is the net present value if the required rate of return is 16 percent? -$311.02 -$1,007.66 $1,168.02 $1,650.11 $2,188.98
The company has a project with a 5-year life, an initial investment of $195,000, and is expected to yield annual cash flows of $56,000. Whathat is the present value index of the project if the required rate of return is set at 10%? Present value index = Total present value of net cash flows Initial investment
please answer all 4 multiple choice questions 5 points COB preferred stock has an 8% stated dividend percentage, and a $100 par value. What is the value of the stock if your required rate of return is per year round to the nearest dollar)? $88.89 $72.73 $66.67 $108.00 $112.50 The discount rate that produces an NPV = 0 is the: Break-even return Conventional return Zero return Base return Internal rate of return 5 points Rossiter Restaurants is analyzing a project...
J&E Enterprises is considering and investment which produces no cash flows for the first year. In the second year, the cash inflow is $47,000. This inflow will increase to $198,000 and then $226,000 for the following two years, respectively, before ceasing permanently. The initial investment will cost $318,000. The firm requires a 15.5 percent rate of return and has a required discounted payback period of three years. Should the project be accepted? Why or why not? show all work Year...
Quad Enterprises is considering a new 3-year expansion project that requires an initial fixed asset investment of $5.886 million. The fixed asset will be depreciated straight-line to zero over its 3-year tax life, after which time it will have a market value of $457,800. The project requires an initial investment in net working capital of $654,000. The project is estimated to generate $5,232,000 in annual sales, with costs of $2,092,800. The tax rate is 24 percent and the required return...