You make fancy, custom l light fixtures. You currently have orders from four important customers. The...

You make fancy, custom l light fixtures. You currently have orders from four important customers. The list below describes the work (the load) that is currently in production, which works 8 hours per day, M-F, with one highly skilled employee. There is no other work in the work center, it is the beginning of the day 3/4, a Monday, no work has been done on any job. Work must be completed by NOON of the day it is due to ship (takes several hours to process and pack a finished item for shipment), so that it can be shipped later in the day or customers can come to pick it up by the end of the day. If it is not done by noon, it cannot ‘ship’ until the next work day. Given the information below, answer the questions listed: (only count working days)

Job

Arrived

Hours to Process

Scheduled Ship Date
(must be done by noon to ship that day)

103

2/22

20

3/5

104

2/25

16

3/14

101

2/20

12

3/13

102

2/21

24

3/4

In what order should the items be built using the shortest operation next rule, and when would each item start and finish, and how late items would be in hours? Fill in the dispatch list table and create a Gantt chart to show this

Dispatch List, in build order:

Decision Criteria Value

Job #

Arrival
date

Process time

Job
Start

Job
Finish

Due date

Late?
Y/N

Hours
late

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The dispatch schedule as per shortest operation next rule is following:

Jobs are scheduled in the order of shortest processing time.

Add a comment
Know the answer?
Add Answer to:
You make fancy, custom l light fixtures. You currently have orders from four important customers. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sager Company manufactures variations of its product, a technopress, in response to custom orders from its...

    Sager Company manufactures variations of its product, a technopress, in response to custom orders from its customers. On May 1, the company had no inventories of work in process or finished goods but held the following raw materials. Material M Material R Paint Total cost 250 units 140 units 85 units @ $260 = @ 220 = @ 105 = $ 65,000 30,800 8,925 $104,725 On May 4, the company began working on two technopresses: Job 102 for Worldwide Company...

  • Sager Company manufactures variations of its product, a technopress, in response to custom orders from its...

    Sager Company manufactures variations of its product, a technopress, in response to custom orders from its customers. On May 1, the company had no inventories of work in process or finished goods but held the following raw materials. Material M 350 units @ $280 $ 98,000 Material R 145 units 30, 450 65 units 7,150 $135,600 210 - 110 - Paint Total cost K On May 4, the company began working on two technopresses: Job 102 for Worldwide Company and...

  • Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two...

    Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $990 $4,530 $3,300 $1,280 Direct...

  • Sager Company manufactures variations of its product, a technopress, in response to custom orders from its...

    Sager Company manufactures variations of its product, a technopress, in response to custom orders from its customers. On May 1, the company had no inventories of work in process or finished goods but held the following raw materials. Material M 350 units @ $ 280 = $ 98,000 Material R 135 units @ 250 = 33,750 Paint 90 units @ 100 = 9,000 Total cost $ 140,750 On May 4, the company began working on two technopresses: Job 102 for...

  • Data Analysis Project Part 1 Custom Fabric Ventures is a small company that produces fabric-based wardrobe...

    Data Analysis Project Part 1Custom Fabric Ventures is a small company that produces fabric-based wardrobe accessories (such as, handbags, scarves, and headbands) and home accessories (such as placemats, pillows, and window treatments).   The company keeps a limited number of popular items in stock, but primarily produces custom orders. Customers are able to choose from a wide selection of styles, sizes, and fabrics for each type of product. Most of the company’s customers are small boutiques, home décor shops, and home-decorators...

  • Instructions Kurtz Fencing Inc. uses a job order costsystem. The following data summarize the operations related...

    Instructions Kurtz Fencing Inc. uses a job order costsystem. The following data summarize the operations related to production for March, the first month of operations a. Materials purchased on account, $45,000. b. Materials requisitioned and factory labor used: Job Materials $1.850 3,150 2.200 1.800 4,230 1.770 1.200 Factory Labor $2,500 7,220 5,350 2,400 6.225 2.000 5,000 306 For general factory use Instructions c. Factory overhead costs incurred on account, $1,800. d. Depreciation of machinery and equipment, $2,500. e. The factory...

  • EC, an engineering company, produces tools and components to customers' specific requirements. EC uses absorption costing...

    EC, an engineering company, produces tools and components to customers' specific requirements. EC uses absorption costing to absorb overheads into the cost of each customer order. Selling prices are usually determined by adding a 30% mark up to the costs incurred in completing the order. EC has recently been asked to provide a quotation for a new customer. The details of the work have been discussed at a meeting with the customer and the following resource requirements have been determined....

  • *****Before you start the problem make sure you multiply the table leg price by four because...

    *****Before you start the problem make sure you multiply the table leg price by four because the table has four legs so the work in process inventory and raw materials for 5-Dec will be $6400.... (Table top=2600)+(Table leg price x 4)+(Drawer)=6400. Make sure to keep in mind the table has four legs. ****** I don't need step 1 i need steps 2,3,4,5,6,7,8 Step 1 You work for Thunderduck Custom Tables Inc. This is the first month of operations. The company...

  • QUESTION THREE [25] EC, an engineering company, produces tools and components to customers' specific requirements. EC...

    QUESTION THREE [25] EC, an engineering company, produces tools and components to customers' specific requirements. EC uses absorption costing to absorb overheads into the cost of each customer order. Selling prices are usually determined by adding a 30% mark up to the costs incurred in completing the order. EC has recently been asked to provide a quotation for a new customer. The details of the work have been discussed at a meeting with the customer and the following resource requirements...

  • Please use the above info to answer the next problems B C D 1 Due to...

    Please use the above info to answer the next problems B C D 1 Due to its popularity, the Black and White Handbag (BW14293) is normally a stock item. However, the 2 handbag is currently out of stock. Rather than producing only enough units to fill Katie's order, 3 management would like to produce a job (Job 114) that is large enough to fill Katie's order and replenish 4 stock. The fabric used for this job can be stacked four...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT