A median run test if performed on a C-Chart. It is determined that of the 16 samples, there were 6 "runs" above and/or below the mean. What is the z-value (ztest) to test whether or not this is in control with respect to runs? Round to 2 decimal places.
Median run test
Sample size, N = 16
Number of observed runs = 6
Expected number of runs = (N/2) + 1 = (16/2) + 1 = 9
Variance = (N/2)*((N/2) - 1)/(N - 1) = 8*(8 - 1)/(16 - 1) = 3.7333
Note: An alternate formula for variance is (N - 1) / 4 which will come = (16 - 1)/4 = 3.75 in this case
So,
Stdev = √3.7333 = 1.932
z-score = (Observed runs - Expected runs) / Stdev = (6 - 9)/1.932 = -1.55
A median run test if performed on a C-Chart. It is determined that of the 16...
Question pertains to the
x-chart part
Sample Mean Range 16 8 12 13 6 6 4 15 10 10 11 10 16 13 14 0 14 17 11 12 IU 12 12 11 13 14 12 7 8 13 9 11 14 7 13 15 10 15 Subsequently, samples of size 5 were taken from the process every week for the next 10 weeks. The times were measured and the following results oblained: Sample Mean Range 16 9 17 12...
Consider the following hypotheses: Ho: mean = 16 Hy: mean < 16 A test is performed with a sample of size 100. The sample mean was 6.33 and the population standard deviation is 60. Assume that the population is approximately normal. Use the TI-84 PLUS calculator to compute the P-value. Round your answer to four decimal places (for example: 0.0138). Write only a number as your answer.
Refer to Table 56.1 - Factors for Computing Control Chart Limits (3 sigma) for this problem. Thirty-five samples of size 7 each were taken from a fertilizer-bag-filing machine at Panos Kouvelis Lifelong Lawn Ltd. The results were: Overall mean = 54.75 16.; Average range R = 1.84 6. a) For the given sample size, the control limits for 3-sigma x chart are: Upper Control Limit (UCL) - b. (round your response to three decimal places). Lower Control Limit (LL)-11. round...
The following is a conrol chart for the average number of minor errors in 22 service reports UCL RFN LCL a. Calculate the observed mean, expected mean, standard deviation and z value for the median and up/down test. (Negative amounts should be indicated by a minus sign. Round your answers to 2 decimal places.) Observed Expected Std. dev Test Median Up/down 12 14.33 2.29 1.89 b. Based on your calculation conclude whether the test is random or non-random. Conclusiorn es...
Problem 6s.11ac Question Help Refer to Table $6.1 - Factors for Computing Control Chart Limits (3 sigma) for this problem. Twelve samples, each containing five parts, were taken from a process that produces steel rods at Emmanual Kodzi's factory. The length of each rod in the samples was determined. The results were tabulated and sample means and ranges were computed. The results were: Sample Sample Mean Range qe (in.) (in.) 9.402 0.033 9.404 0.041 9.391 0.034 9.408 0.051 9.399 0.031...
Refer to Table 56.1 - Factors for Computing Control Chart Limits (sigma) for this problem. Thirty-five samples of size 7 each were taken from a fertilizer-bag-filling machine at Panos Kouvels Lifelong Lawn Lid. The results were: Overal mean = 54.75 lb.: Average range R 164 b. a) For the given sample size, the control limits for 3-sigma x chart are Upper Control Limit (UCL) - D. (round your response to three decimal places). Lower Control Limit (LCL)-1. (round your response...
The centerline of a c control chart is determined to be 16. Based on these information, an observed c of 25 indicates a. The process is in control because the observed c is greater than the lower control limit of 4 b. The process is in control because the observed c is smaller than the upper control limit of 28 c. The process is in control because the observed c is between the lower control limit of 4 and the...
Table A Areas under the normal curve, 0 to z 03 Z 00 0080 0120 01 0478 0517 15 16 19 o00 DI 02 E# e.What alpha risk would control limits of .0470 and .0136 provide? (Round your intermediate calculations to 4 decimal places. Round your "z" value to 2 decimal places and "alpha risk" value to 4 decimal places.) 1, alpha risk z= fUsing control limits of .0470 and .0136, is the process in control? ook Oyes rint Ono...
Suppose we are interested in whether there is a dierence between the median numbers of hours spent each week by men and woman watching television. Two random samples were taken: the numbers of hours taken by men and women watching television are shown below. You are about to test the null hypothesis that there is no dierence in weekly television watching hours between men and woman. Men: 5 10 12 15; Women: 0 7 4 3 6 8 a) calculate...
Smith and Johnson Industries has decided to use a p-Chart with 3-sigma control limits to monitor the proportion of defective galvanized pipes produced by their production process. The quality control manager randomly samples 150 galvanized pipes at 16 successively selected time periods and counts the number of defective galvanized pipes in the sample. Step 1 of 8: What is the Center Line of the control chart? Round your answer to three decimal places. Step 2 of 8: What value of...