Question

A manufacturing firm has set up a project for developing a new machine for one of...

A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation cost exceed 1,425,000, the project will not meet the firm’s NPV hurdle. There are four cost categories involved in adding the prospective new machine to the production line: (1) engineering labor cost, (2) non-engineering labor cost, (3) assorted materials cost, and (4) production line down-time cost. The engineering labor requirement has been estimated to be 600 hours, plus or minus 15% at a cost of $80 per hour. The non-engineering labor requirement is estimated to be 1500 hrs., but could be as low as 1200 hrs. or as high as 2200 hrs. at a cost of $35 per hour. Assorted material may run as high as $155,000 or as low as $100,000 but is most likely to be about $135,000. The best guess of time lost on the production line is 110 hours, possibly as low as 105 hours and as high as 120 hours. The line contributes about $500 per hour to the firms profit and overhead. What is the probability that the new machine project will meet the firm’s NPV hurdle? Use Crystal Ball simulation to answer the question.

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
A manufacturing firm has set up a project for developing a new machine for one of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A manufacturing firm has set up a project for developing a new machine for one of...

    A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation cost exceed 1,425,000, the project will not meet the firm’s NPV hurdle....

  • You are considering a proposal to produce and market a new sluffing machine. The most likely...

    You are considering a proposal to produce and market a new sluffing machine. The most likely outcomes for the project are as follows: Expected sales: 115,000 units per year Unit price: $220 Variable cost: $132 Fixed cost: $4,890,000 The project will last for 10 years and requires an initial investment of $16.70 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 30%, and the required rate of return...

  • Problem 11-12 New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would...

    Problem 11-12 New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the...

  • New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax...

    New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5-year...

  • Problem 11-12 New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would...

    Problem 11-12 New-Project Analysis Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the...

  • Acme Equipment Company is considering the development of a new machine that would be marketed to tire manufacturers. Res...

    Acme Equipment Company is considering the development of a new machine that would be marketed to tire manufacturers. Research and development costs for the project as expected to be about $4 million but could vary between $3 and $6 million. The market life for the product is estimated to be 3 to 8 years with all intervening possibilities being equally likely. The company thinks it will sell 250 units per year, but acknowledges that this figure could be as low...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $433,000 is estimated to result in $163,000 in annual pretax cost savings. The press is eligible for 100 percent bonus depreciation and it will have a salvage value at the end of the project of $64,000. The press also requires an initial investment in spare parts inventory of $16.900. along with an additional $3,900 in inventory for each succeeding year of...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $796800 is estimated to result in $265600 in annual pretax cost savings. The press falls in the MACRS (MACRS Table) five-year class and it will have a salvage value at the end of the project of $116200. The press also requires an initial investment in spare parts inventory of $33200, along with an additional $4980 in inventory for each succeeding year...

  • The management of Devine Instrument Company is considering the purchase of a new drilling machine, model...

    The management of Devine Instrument Company is considering the purchase of a new drilling machine, model RoboDril 1010K. According to the specifications and testing results, RoboDril will substantially increase productivity over AccuDril X10, the machine Devine is currently using. The AccuDril was acquired 8 years ago for $110,000 and is being depreciated using the straight-line method over a 10-year expected life and an estimated salvage value of $30,000. The engineering department expects the AccuDril to keep going for another 3...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $415,000 is estimated to result in $154,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $55,000. The press also requires an initial investment in spare parts inventory of $16,000, along with an additional $3,000 in inventory for each succeeding year...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT