A construction equipment dealer is facing a difficult inventory problem. Low inventory turnover is squeezing profit...

A construction equipment dealer is facing a difficult inventory problem. Low inventory turnover is squeezing profit margins and causing cash-flow problems. One of the top-selling SKUs in the storage is a special small appliance. Sales are 18 units per week, and the supplier charges $60 per unit. The cost of placing an order with the supplier is $45. Annual holding cost is 25 percent of a product’s value, and the shop operates 52 weeks per year. Management chose a 390-unit lot size so that new orders could be placed less frequently.

A)- Determine EOQ

B)- What is the annual cycle-inventory cost of the current policy of using a 390-unit lot size? Would a lot size of 468 be better?

C)- Suppose that the average demand is 18 units per week with a standard deviation of 5 units. The lead time is constant at 2 weeks. Determine the safety stock and reorder point if management wants a 90 percent cycle - service level.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Average weekly demand (d) = 18 units

Number of weeks per year = 52

Annual demand (D) = d x number of weeks per year = 18 x 52 = 936 units

Ordering cost (S) = $45

Holding cost (H) = 25% of cost = 25% of $60 = $15

Current order quantity = 390 units

A) Economic order quantity = √(2DS/H)

= √[2 X 936 X 45) /15]

= √(84240/15)

= √5616

= 75 units

B) With order quantity (Q) = 390 units

Annual ordering cost= (D/Q) S = (936/390) 45 = $108

Annual holding cost = (Q/2) H = (390/2) 15 = $2925

Annual cycle inventory cost with the current policy = $108 + $2925 = $3033

With order quantity(Q) = 468 units

Annual ordering cost = (D/Q) S = (936/468) 45 = $90

Annual holding cost (Q/2) H = (468/2) 15 = $3510

Total annual cost = $90+$3510 = $3600

So a lot size of 468 would not be better as it has a higher total cost than the lot size of 390 units

C) standard deviation of weekly demand (d) = 5 units

Lead time (L) = 2 weeks

At 90% service level value of Z = 1.28

Safety stock = Z x d x √L = 1.28 x 5 x √2 = 1.28 x 5 x 1.41 = 9.02 or rounded to 9 units

Reorder point = d x L + safety stock

= 18 x 2 + 9

= 36 + 9

= 45 units

Add a comment
Know the answer?
Add Answer to:
A construction equipment dealer is facing a difficult inventory problem. Low inventory turnover is squeezing profit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Petty House operates 52 weeks per year, 6 days per week, and uses a continuous review inventory

    Petty House operates 52 weeks per year, 6 days per week, and uses a continuous review inventory system (i.e. Q system). It purchases kitty litter for $ 10 per bag. The following information is available about these bags. Demand = 102 bags/ week Order cost = $ 49/ order Annual holding cost = 25 percent of cogs Desired cycle service level = 80 percent Lead time = 3 weeks Standard deviation of weekly demand = 15 bags Current on-hand inventory...

  • Sam's Cat Hotel operates 52 weeks per year, 7 days per week, and uses a continuous...

    Sam's Cat Hotel operates 52 weeks per year, 7 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.75 per bag. The following information is available about these bags. Demand = 95 bags/week Order cost = $58/order Annual holding cost = 25 percent of cost Desired cycle@service level = 90 percent Lead time = 4 weeks (28 working days) Standard deviation of weekly demand = 16 bags Current on-hand inventory is 315 bags, with...

  • A local store sells toilet paper to people in the surrounding communities. The demand for the...

    A local store sells toilet paper to people in the surrounding communities. The demand for the toilet paper has been increasing and management needs to ensure that enough rolls are available to meet the increasing demand. The daily demand for the toilet paper is 400 rolls. The store operates 250 days per year. The following information is also available about the product. The cost of each roll……………………….…..$2. Ordering costs………………………………..……$100 per order Annual holding costs per unit…………… 10% of the costs...

  • A firm is operating a fixed inventory system. One product has the following characteristics: Order cost...

    A firm is operating a fixed inventory system. One product has the following characteristics: Order cost $35/order Unit cost $15/unit Holding cost/unit/year 20% of unit cost Annual demand 1800 Lead time 2 weeks Answer the following questions: a. What is the optimal order quantity, EOQ? b. What is the total annual inventory cost? c. If management decides to use order size of 400 rather than the EOQ, what will be the impact on total cost? (Calculate) c. If demand is...

  • 3. One of the top-selling items in the container group at the museum’s gift shop is...

    3. One of the top-selling items in the container group at the museum’s gift shop is a birdfeeder. Sales are 18 units per week, and the supplier charges $60 per unit. The cost of placing an order with the supplier is $45. Annual holding cost for each unit is 25 percent of a feeder’s value, and the museum operates 52 weeks per year. Management currently chose to order 390 units when they place an order. What is the annual cost...

  • Eagle Insurance is a large insurance company chain with a central inventory operation. The company’s fastest-moving...

    Eagle Insurance is a large insurance company chain with a central inventory operation. The company’s fastest-moving inventory item has a demand of 80,000 units per year. The cost of each unit is $200, and the inventory carrying cost is $15 per unit per year. The average ordering cost is $60 per order. It takes about 2 days for an order to arrive. This is a corporate operation, and there are 250 working days per year. (Please show all work including...

  • ​Sam's Cat Hotel operates 52 weeks per​ year and uses a continuous review inventory system. It...

    ​Sam's Cat Hotel operates 52 weeks per​ year and uses a continuous review inventory system. It purchases kitty litter for ​$10.75 per bag. The following information is available about these bags. Demand = 85 bags/week Order cost = $57/order Annual holding cost = 26% of cost per bag Desired cycle-service level = 90% Lead-time = 2 weeks Standard deviation of weekly demand = 18 bags What is the economic order quantity (EOQ) for kitty litter? What would be the average...

  • Using a computerized Inventory Management System, a Paint Supply Store franchise continuously monitors the inventory of...

    Using a computerized Inventory Management System, a Paint Supply Store franchise continuously monitors the inventory of all the paint located at each of their 15 stores and their distribution warehouse. The Paint Supply Store franchise sells an average of 64 gallons of Green Paint every week (for 52 weeks per year). They purchase Green Paint from their supplier at a price of $3.50 per gallon. [The company does not hold Safety Stock] It takes 2.25 weeks to receive an order...

  • Problem 14.28 (additional/static) Keebock, a maker of outstanding running shoes, keeps the soles of its size-13 running...

    Problem 14.28 (additional/static) Keebock, a maker of outstanding running shoes, keeps the soles of its size-13 running shoes in inventory for one period at a cost of $0.25 per unit. The setup costs are $50. Beginning inventory is zero and lead time is 1 week. Shown below are the net requirements per period. Period 1 2 4 5 910 Net requirements 35 30 45 010 40 30 030 55 a) Keebock's cost based on EO is (round your response to...

  • An automobile manufacturer stocks a certain inventory item. The daily demand for the inventory item is...

    An automobile manufacturer stocks a certain inventory item. The daily demand for the inventory item is 20 units. The company estimates its annual holding cost for this item to be $10 per unit. The cost to place and process an order from the supplier is $200. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days on average. (a)    Find the economic order quantity. (b)    Find...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT