Question

How is a project baseline used to guide the execution of the project's work, to evaluate...

How is a project baseline used to guide the execution of the project's work, to evaluate progress and performance, and to control the project? How can the project baseline and the earned value approach for variance analysis be used to monitor and report project progress?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer-

Project baseline refers to the set of stored values that govern project execution. They include initially scheduled start and finish periods, planned effort, budgeted cost, and projected revenue. The primary benefits of using a project baseline are the capacity to evaluate the performance, earn value control, and enhanced future approximating accuracy. When project necessities have been assessed and recorded, and the project-planning baseline has been developed for cost, scope, and agenda, project implementation and control operations can start. The process entails the application of traditional system control systems to the project exertion. Bearing in mind the project effort to be a procedure, the tactics, stipulations, resources, and techniques are the inputs. The process yields need to be frequently supervised and associated with the plan. Alterations in the process need to conform to the scheme’s output as anticipated. Variance between project outcomes and the plan need to be evaluated and recorded sporadically.

Add a comment
Know the answer?
Add Answer to:
How is a project baseline used to guide the execution of the project's work, to evaluate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following project activities, their cost, baseline time, actual time spent, and estimated time to...

    Consider the following project activities, their cost, baseline time, actual time spent, and estimated time to completion: Task Estimated Cost per hour Baseline Duration Actual Time Spent Estimated Time to Completion A $75 14 hr 15 hr 1 hr B $92 19 hr 18 hr 2 hr C $135 11 hr 9 hr 2 hr D $110 13 hr 13 hr 1 hr Calculate the following project values showing your work: Planned Value Actual Cost Earned Value Schedule Variance Cost...

  • You are using earned value analysis to track your project's progress. In your project, earned value...

    You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget. Select an answer: behind; under ahead of; under ahead of: over behind; over

  • As a project goes through the execution phase, project control is critical to ensure that a...

    As a project goes through the execution phase, project control is critical to ensure that a project stays within the constraints of time, cost, and scope. A project manager will use different monitoring techniques to help keep the project within these constraints. If a project incurs changes, becomes delayed, or costs become higher, a project manager will execute change control to document and determine how to handle the change. Once a project is completed, the project team should complete a...

  • Project Monitoring and Control (Chapter 8) 10. What are the benefits and drawback with the use...

    Project Monitoring and Control (Chapter 8) 10. What are the benefits and drawback with the use of milestone analysis as a monitoring tool? 11. What are the two basic components of project control? 12. Compare and contrast the use of calendar and working days for project schedules. When are each best used and why? 13. Discuss the different ways progress on projects can be monitored. 14. Why is a schedule baseline critical to project success? Under what conditions would a...

  • In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting...

    In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting the overall schedule and budget of a project?

  • IT Project Management: Chapter 7 Project Cost Management: 1. In general, ____________________ numbers for cost and...

    IT Project Management: Chapter 7 Project Cost Management: 1. In general, ____________________ numbers for cost and schedule variance indicate problems in those areas. 2. ____ is a project performance measurement technique that integrates scope, time, and cost data. a. Cost baseline b. Earned value management c. Constructive cost modeling d. Parametric modeling 3. Information technology project managers need to be able to present and discuss project information in ____________________ terms as well as in technical terms. 4. Project managers should...

  • A road resurfacing and barrier protection project, planned to take 30 weeks to complete, is underway....

    A road resurfacing and barrier protection project, planned to take 30 weeks to complete, is underway. Week 35 of the project has just ended. You are to use the Earned Value Analysis technique with the data provided in Table A1, to monitor the project's progress and answer the following question: a) Assuming nothing changes, work out the new total estimated cost at completion and the new to estimated time at completion (to 1 decimal place). D) What does your answer...

  • Klott Company used scenario analysis to evaluate a capital budgeting project. The analysis generated a net...

    Klott Company used scenario analysis to evaluate a capital budgeting project. The analysis generated a net present value (NPV) equal to $10,500 and a standard deviation (σ) equal to $12,083. The project's coefficient of variation (CVNPV) is _____. Group of answer choices 1.15 0.25 0.87 10.50 13.90

  • 4. You are the project finance manager on a project that is coming in over budget...

    4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT