Question

In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting...

  1. In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting the overall schedule and budget of a project?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

A project is an activity that has been undertaken by the company for the first time in order to achieve something new. There are project teams that work on achieving the goal of the project. They work under the guidance of the project manager. The project manager monitors the activities that are carried out as a part of the project and uses several techniques for this. One such evaluation of project technique is Earned Value Analysis.

The Earned Value Analysis is a good method of monitoring the project. It sets the objective that the project has to achieve and it also mentions the standards by which the project work is evaluated. It sets goals and also gives directions as to how the project work has been progressing. The whole work is broken down into smaller components so that the measurement can be done easily. There is also a clear time frame set for each actitvity along with the cost involved in each activity. The project manager compares the achieved level with the target set and then evaluates the project. Similarly, the cost that is incurred in reality is compared with the target cost for evaluation of the project. Thus, the overall schedule and the budget of the project is not affected when the evaluation of the project progress is done by Earned Value Analysis.

Add a comment
Know the answer?
Add Answer to:
In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are using earned value analysis to track your project's progress. In your project, earned value...

    You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget. Select an answer: behind; under ahead of; under ahead of: over behind; over

  • to have Earned Value Analysis (EVA) prove valuable in the project, you need to accurately collect...

    to have Earned Value Analysis (EVA) prove valuable in the project, you need to accurately collect information about the status of each task and the on-going project costs. What are some processes that can be used to collect data fo computing EV and AC? How can you ensure that collecting cost and schedule information is not so cumbersome that it almost results in the need for a project task be added to the plan just to accommodate the process?

  • In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider...

    In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider the following situation. A project has a planned schedule of 12 months with an estimated project cost of $800,000 . At six months into the project, the project manager quits and you are asked to take over the project. You discover that the accumulated costs are already $200,000 but only 25% of the work is complete. What is the schedule variance for this project?...

  • How is a project baseline used to guide the execution of the project's work, to evaluate...

    How is a project baseline used to guide the execution of the project's work, to evaluate progress and performance, and to control the project? How can the project baseline and the earned value approach for variance analysis be used to monitor and report project progress?

  • agree or not ? what is one-way analysis of variance used for? One way analysis of...

    agree or not ? what is one-way analysis of variance used for? One way analysis of variance is basically a method that is used in order to see if there are any significant differences between the means of the unrelated groups. "It is a method of testing the equality of three or more population means by analyzing sample variances"(Triola, M, 2018). what is the main difference between one-way analysis of variance and two-way analysis of variance? The main difference is...

  • A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both...

    A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $10. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the estimate at completion (EAC) of the project? $12.96 $13.17 $14.75 $15 What is your reasoning? ________________________________________________________

  • Q1- Part A- Which of the following can best describe the project status in regard to...

    Q1- Part A- Which of the following can best describe the project status in regard to budget and schedule? a- Behind schedule-Overbudget b- Behind schedule- Underbudget c- Ahead the schedule- Overbudget d- Ahead of schedule- Underbudget Part B- It is possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance. TRUE or FALSE Part C EV is cost-based, so it is more reliable than CPM. TRUE of...

  • Project Monitoring and Control (Chapter 8) 10. What are the benefits and drawback with the use...

    Project Monitoring and Control (Chapter 8) 10. What are the benefits and drawback with the use of milestone analysis as a monitoring tool? 11. What are the two basic components of project control? 12. Compare and contrast the use of calendar and working days for project schedules. When are each best used and why? 13. Discuss the different ways progress on projects can be monitored. 14. Why is a schedule baseline critical to project success? Under what conditions would a...

  • 1. Describe two methods that can be used to determine the critical path of a project...

    1. Describe two methods that can be used to determine the critical path of a project schedule. 2. If an activity on the critical path falls behind schedule, what effect will this have on the entire project? 3. Describe the relationship between a predecessor project activity and a successor project activity. management. 4. Using the enumeration method, explain how a project critical path can be determined. Support your response with an illustrative chart.

  • What is one disadvantage of NPV as a capital budget method? It does not deliver an...

    What is one disadvantage of NPV as a capital budget method? It does not deliver an overall picture of the gain or loss of implementing a project. It can be misleading if inputs like cash flow turn out to be wrong. It is rarely used, so there is disagreement as to what an adequate NPV is. It cannot be used to compare investments with different upfront costs.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT