Question

In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider...

In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider the following situation. A project has a planned schedule of 12 months with an estimated project cost of $800,000 . At six months into the project, the project manager quits and you are asked to take over the project. You discover that the accumulated costs are already $200,000 but only 25% of the work is complete. What is the schedule variance for this project?

12 months

$600,000

-$200,000

6 months

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Earned value = 25% of work is completed = 25% of 8,00,000 = $2,00,000

Planned value = (completed time/total time planned) * total budget =(6/12) * 8,00,000 = $4,00,000

Schedule variance = Earned value - Planned value = 2,00,000 - 4,00,000 = -$2,00,000

Hence the correct answer is 3rd option i.e., -$200,000

Add a comment
Know the answer?
Add Answer to:
In earned value analysis the "schedule variance" is the earned value minus the planned value. Consider...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are using earned value analysis to track your project's progress. In your project, earned value...

    You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget. Select an answer: behind; under ahead of; under ahead of: over behind; over

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • Given the following information and formulae from the lecture, calculate earned value cost variance, and schedule...

    Given the following information and formulae from the lecture, calculate earned value cost variance, and schedule variance: Rate of performance: 45% Planned value: $20000 Actual cost: $40000

  • For a project, in X day, planned value, earned value and actual cost of the tasks...

    For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...

  • Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated...

    Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated each month. It demonstrates the cost and schedule status of a project at a given moment in time. Answer the questions associated with the accompanying C/SSR after reading the appropriate sections on earned value in Managing Projects in Organizations, The New Project Management, and A Guide to the Project Management Body of Knowledge (PMBOK). Task Budget Task begun Task ended Actual Cost A 30,000...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it Page 6 of 8 IS8100-01 Fa2019 under or over budget? Use all of the calculated variances and indexes from above to support your argument. [50-100-word response.]

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT