Question

Q1- Part A- Which of the following can best describe the project status in regard to...

Q1-

Part A-

Which of the following can best describe the project status in regard to budget and schedule?

a- Behind schedule-Overbudget

b- Behind schedule- Underbudget

c- Ahead the schedule- Overbudget

d- Ahead of schedule- Underbudget

Part B-

It is possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance.

TRUE or FALSE

Part C

EV is cost-based, so it is more reliable than CPM.

TRUE of FALSE

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans 1 : D) Ahead of schedule- Underbudget

Ans 2 : False , It is not possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance.

Ans 3 : True , Earned Value Analysis is cost-based, so it is more reliable than CPM.

Add a comment
Know the answer?
Add Answer to:
Q1- Part A- Which of the following can best describe the project status in regard to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT