Question

6. A contract for your project is Firm Fixed Price. The negotiated price is $50,000. If...

6. A contract for your project is Firm Fixed Price. The negotiated price is $50,000. If the actual cost is $40,000, what is the total payment owed to the supplier?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Given that:

Actual cost = $40,000

Negotiated price = $50,000

Explanation:

Payment owed to supplier

= Actual costs + negotiated fee

=$40,000 + $50,000

=$90,000.

Add a comment
Know the answer?
Add Answer to:
6. A contract for your project is Firm Fixed Price. The negotiated price is $50,000. If...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The target cost of a fixed price contract is $50,000. The price of the contract is...

    The target cost of a fixed price contract is $50,000. The price of the contract is targeted at $75,000 with a ceiling price of $100,000. The share ratio is 80/20. What is the Point of Total Assumption of this procurement? $100,000 $125,000 $81,250 $112,500

  • Consider a construction project for which the target estimate is $10,000,000. The contract is a guaranteed...

    Consider a construction project for which the target estimate is $10,000,000. The contract is a guaranteed maximum price contract (GMP including fee = $11,000,000). Calculate the owner’s payment and the contractor’s earnings if the contract’s actual costs (excluding fee) is $11,500,000? Assume that this cost includes change orders worth $250,000. According to the contract, the change orders will be in addition to negotiated GMP but the contractor will not be compensated for the first $150,000 of change orders.

  • You have been asked to price out a project for a customer based on a firm-fixed...

    You have been asked to price out a project for a customer based on a firm-fixed price. Table below shows the numbers that you arrived at in determining the bid amount for the project that should be submitted. As you know, before a bid is submitted to a potential customer, the bid must be reviewed by a committee of senior managers that can question the validity of the numbers as well as look for “hidden” costs that may have been...

  • A fixed price contract including a profit of 340,000 totals 4.6 million with no reserve. In...

    A fixed price contract including a profit of 340,000 totals 4.6 million with no reserve. In a progress report the CEV was given as 2.75 million and actual cost was 2.8 million. What is the forecasted (estimated) profit in units of currency using forecasting based on the assumption that cost performance on the contract to date will continue for the remainder of the project?

  • UNITS PRODUCED AND SOLD 50,000 100,000 200,000 TOTAL COSTS VARIABLE COSTS FIXED COSTS 50,000 TOTA...

    UNITS PRODUCED AND SOLD 50,000 100,000 200,000 TOTAL COSTS VARIABLE COSTS FIXED COSTS 50,000 TOTAL COSTS COST PER UNIT VARIABLE COST FIXED COST 50.25 TOTAL COST PER UNIT ASSUME THE COMPANY SELLS 200,000 UNITS FOR S1/UNIT PREPARE A CONTRIBUTION FORMAT INCOME STATEMENT 1 cost behavior patterns include: (aj variable costs (b)fixed costs (c) mixed costs (d) all of the above 2 fixed costs: (a) remain the same in total (b) vary per unit (c) remain constant per unit (d) vary...

  • A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate...

    A Client has decided to use a Cost Plus Incentive Fee contract price arrangement to motivate the Contractor to be more efficient and productive in executing the project. The Contractor’s Fee will be calculated based on a Sliding Fee approach by considering a $110,000,000 target price and a 4% Base (R). Calculate Contractor’s Fee and Total Payment to the Contractor for two following scenarios: Scenario 1) Actual Cost of Project = $102,000,000 Scenario 2) Actual Cost of Project = $124,000,000

  • 2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes...

    2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2018 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2018 $ 135 Cash collected on project during 2018 $ 105 Construction in progress, 12/31/2018 $ 207 Estimated percentage of completion during 2018 60 % 1.How much revenue (in millions) is...

  • only numbers 2,3, and 6 You are trying to decide a present worth of a contract....

    only numbers 2,3, and 6 You are trying to decide a present worth of a contract. You will receive $10,000 when the contract is signed, a $20,000 payment at the end of Year 1, and $30,000 at the end of Year 2. and $40,000 at the end of Year 3, and $50,000 at the end of Year 4 when the project is completed. Your annual costs for this project are $10,000 per year. What is the present worth of the...

  • A bank teller negotiated a purchase price of $22,350 for a car.  In addition to the purchase...

    A bank teller negotiated a purchase price of $22,350 for a car.  In addition to the purchase price, the teller had to pay sales tax that was 6.25% of the purchase price and a $452 license fee. If the teller makes a down payment of 10% of the total cost of the car and secures a 4-year loan at an annual interest rate of 4.9% compounded monthly, what is the monthly car payment?

  • A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed...

    A Cost Plus Fixed Fee (CPFF) Contract has an estimated Cost of $55,000,000 and a Fixed Fee of $5,000,000. What is the final price and the ROS if : a.) The actual cost is $48,000,000 b.) The actual cost is $75,000,000

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT