If an investment project has an internal rate of return equal to the required rate of return, the NPV for the project:
A. may be either positive or negative
B. is positive
C. cannot be determined
D. is zero
E. is negative
By the definition of IRR only, we know that IRR is that discount rate which makes the NPV (net Present value) of all cashflows equal to zero.
Hence, if required rate of return (WACC) is equal to IRR, then NPV of the project will be ZERO (option D).
If an investment project has an internal rate of return equal to the required rate of...
4. If an investment project has an IRR equal to the interest rate, the NPV for that project a. is positive b. is negative c. is zero. The NPV vs. r graph shows this best. d. may be negative or positive
8) Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required retum of 12 percent. Which of the following statements is MOST correct? A) Project A must have a higher NPV than Project B. B) Both projects have a positive net present value (NPV) C) Project B has a higher profitability index than Project A. D) If the required return were less than 12 percent,...
If an investment project (with conventional cash flows) has IRR equal to the cost of capital, the NPV for that project is: Positive Negative Zero Unable to determine Question 13 (2 points) The following are measures used by firms when making capital budgeting decisions except: Payback period Internal rate of return P/E ratio 1. Net present value
The point where a project produces a rate of return equal to the required return is known as the: A) present value break-even point. B) accounting break-even point. C) point of zero profit. D) internal break-even point. E) income break-even point.
18. Which of the following is NOT true about the internal rate of return: A) A good project is one with IRR greater than the required return. B) IRR is the discount rate that results in a zero net present value for the project. C) Crossover rate for two projects is the IRR of the project with the difference of the cash flows of the two projects.. D) For two projects of the same size, IRR will usually choose the...
An investment of $1,000 will return $60 annually forever. What is its internal rate of return? Please show work. A. Cannot be determined. B. 6% C. 0.60% D. 16.67% E. 60%
48. The internal rate of return of an investment is: A. the same as return on investment. B. zero when the present value of an investment equals its cost. C. the interest rate that equates the present value of an investment with its cost D. equal to the market rate of interest when an investment is made
Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a cost of capital of 12 percent. Which of the following statements is most correct? Question 3 options: Both projects have a positive net present value (NPV). Project A must have a higher NPV than Project B. If the cost of capital were less than 12 percent, Project B would have a higher IRR than Project A....
The internal rate of return is best described as that discount rate that _______ A equates the NPV and IRR B makes NPV equal zero C. equals the required rate of return D. equates all cash flows to the current market rate
Internal rate of return (IRR) is computed by finding the discount rate that will cause a. NPV of a project to be zero b. NPV of a project to be greater than zero c. NPV of a project to be less than zero d. IRR of a project to be zero Select one: a. NPV of a project to be less than zero b. NPV of a project to be zero c. NPV of a project to be greater than...