Question

If an investment project (with conventional cash flows) has IRR equal to the cost of capital, the NPV for that project is: Po
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q-12:

Zero

IRR is the internal rate of return of a given project, whereas the cost of capital is its required rate, when both are the same then the return is exactly zero.

Q-13:

P/E ratio

Payback period, internal rate of return and NPV are the methods that are used to evaluate capital budgeting decisions but not PE ratio.

Add a comment
Know the answer?
Add Answer to:
If an investment project (with conventional cash flows) has IRR equal to the cost of capital,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is...

    Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is 15.7 percent, NPV is -$198, and the payback period is 3.92 years. Which one of the following statements is correct given this information? This project should be accepted based on the internal rate of return. The discount rate used in computing the net present value was less than 15.7 percent. The required rate of return must be greater than 15.7 percent. The discounted payback...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,750,000. The project's expected cash flows are: Year Year 1...

  • 7) Which of the following statements is FALSE? A) The IRR investment rule will identify the...

    7) Which of the following statements is FALSE? A) The IRR investment rule will identify the correct decision in many, but not all, situations. B) By setting the NPV equal to zero and solving for r, we find the IRR. C) If you are unsure of your cost of capital estimate, it is important to determine how sensitive your analysis is to errors in this estimate. D) The simplest investment rule is the NPV investment rule. 8) Which of the...

  • F a company is in the situation of having unlimited capital funds, the best decision rule, consid...

    f a company is in the situation of having unlimited capital funds, the best decision rule, considering only financial factors, is for the company to invest in all projects in which: The payback period is short. The accounting (book) rate of return (ARR) is greater than its current return on invested capital (ROI). The net present value (NPV) is greater than the cost of capital. The internal rate of return (IRR) is greater than zero. The NPV is greater than...

  • For a typical capital investment project, the bulk of the investment-related cash outflow occurs: During the...

    For a typical capital investment project, the bulk of the investment-related cash outflow occurs: During the initiation stage of the project During the operation stage of the project Either during the initiation stage or the operation stage During neither the initiation stage nor the operation stage Evenly during all three stages: initiation, operation, and final disposal The time value of money is explicitly considered in which of the following capital budgeting methods? Payback method Net present value (NPV) method Operating...

  • 4. If an investment project has an IRR equal to the interest rate, the NPV for...

    4. If an investment project has an IRR equal to the interest rate, the NPV for that project a. is positive b. is negative c. is zero. The NPV vs. r graph shows this best. d. may be negative or positive

  • Capital Budgeting Analysis : A firm is planning a new project that is projected to yield cash flo...

    Capital Budgeting Analysis : A firm is planning a new project that is projected to yield cash flows of - $595,000 in Year 1, $586,000 per year in Years 2 through 5, and $578,000 in Years 6 through 11. This investment will cost the company $2,580,000 today (initial outlay). We assume that the firm's cost of capital is 11%. (1) Draw a timeline to show the cash flows of the project. (2) Compute the project’s payback period, net present value...

  • You must know all the cash flows of an investment project to compute its NPV, IRR,...

    You must know all the cash flows of an investment project to compute its NPV, IRR, PI and payback period OA NPV, PI, IRR ОВ. Ос. OD IRR, PI payback period and discount payback period NPV, IRR, PI payback period, and discount payback period IRR, PI and payback period NPV, IRR, PI and discount payback period OE. OF.

  • Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all...

    Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all other cash flows are positive). Which of the following statements is most correct? All else equal, a project's IRR increases as the required rate of return declines. All else equal, a project's IRR increases as the required rate of return increases All else equal, a project's NPV increases as the required rate of return declines. None of the above Question 11 (2 points) Suppose...

  • 1. The most popular capital budgeting techniques used in practice to evaluate and select projects are...

    1. The most popular capital budgeting techniques used in practice to evaluate and select projects are payback period, Net Present Value (NPV), and Internal Rate of Return (IRR). 2. Payback period is the number of years required for a company to recover the initial investment cost. 3. Net Present Value (NPV) technique: NPV is found by subtracting a project’s initial cost of investment from the present value of its cash flows discounted using the firm’s weighted average cost of capital....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT