Question



You must know all the cash flows of an investment project to compute its NPV, IRR, PI and payback period OA NPV, PI, IRR ОВ.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

an investment its :- you must know all the cash flows of project to compute NPV, PI, IRR. ( option B) Ans: Initial outlay NPV

Add a comment
Know the answer?
Add Answer to:
You must know all the cash flows of an investment project to compute its NPV, IRR,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You must know the required return to compute the project’s A. NPV, IRR, PI, and discounted...

    You must know the required return to compute the project’s A. NPV, IRR, PI, and discounted payback period B. NPV, PI, IRR C. NPV, IRR, discount payback period D. NPV, PI, discounted payback period E. IRR, PI, discounted payback period

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85.000 and expected free cash flows of ​$20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash...

    (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?

  • A project has a profitability index (PI) of 1.1. If the initial investment of $10,000. What do you know about the NPV and IRR? a) NPV may be smaller than zero b)NPV must be $1000 c) The IRR is the pre...

    A project has a profitability index (PI) of 1.1. If the initial investment of $10,000. What do you know about the NPV and IRR? a) NPV may be smaller than zero b)NPV must be $1000 c) The IRR is the prevailing discount D) none of the above

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85 comma 000 and expected free cash flows of ​$30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows...

    This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...

  • you are considering a project with an initial cash outlay of $74,000 and expected cash flows...

    you are considering a project with an initial cash outlay of $74,000 and expected cash flows of $23,680 at the end of each year for six years. the discount rate for the project is 9.7 percent. a. what are the project's payback discounted payback periods? - if the discount rate for this project is 9.7 percent, the discounted payback period of the project is how many years? b. what is the projects NPV? c. what is the project's PI? d....

  • Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR,...

    Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent.                 Year                                  CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00

  • Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is...

    Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is 15.7 percent, NPV is -$198, and the payback period is 3.92 years. Which one of the following statements is correct given this information? This project should be accepted based on the internal rate of return. The discount rate used in computing the net present value was less than 15.7 percent. The required rate of return must be greater than 15.7 percent. The discounted payback...

  • 1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR,...

    1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year                Cash Flow                 Net Profit                   Depreciation 0                    -$125,000 1                    $22,000                     $15,000                      $10,000 2                    $58,000                     $43,000                      $25,000 3                    -$30,000                   $24,000                      $21,000 4                    $35,000                     $28,000                      $18,000 5                    $28,000                     $20,000                      $15,000 6                    $60,000                     ...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT