Question

Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is 15.7 percent, NPV is -$198, and th
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct statement is

The required rate of return must be greater than 15.7%

NPV is zero at IRR

Since NPV is negative, Rate of return is higher than IRR

Project should not be accepted on the basis of IRR since IRR is lower than WACC

The discounted payback period is always higher than regular payback period due to discounting of cash flows

Hence, all other statements are FALSE

Add a comment
Know the answer?
Add Answer to:
Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • you are considering a project with an initial cash outlay of $74,000 and expected cash flows...

    you are considering a project with an initial cash outlay of $74,000 and expected cash flows of $23,680 at the end of each year for six years. the discount rate for the project is 9.7 percent. a. what are the project's payback discounted payback periods? - if the discount rate for this project is 9.7 percent, the discounted payback period of the project is how many years? b. what is the projects NPV? c. what is the project's PI? d....

  • If an investment project (with conventional cash flows) has IRR equal to the cost of capital,...

    If an investment project (with conventional cash flows) has IRR equal to the cost of capital, the NPV for that project is: Positive Negative Zero Unable to determine Question 13 (2 points) The following are measures used by firms when making capital budgeting decisions except: Payback period Internal rate of return P/E ratio 1. Net present value

  •  You are considering a project with an initial cash outlay of ​$75,000 and expected cash flows...

     You are considering a project with an initial cash outlay of ​$75,000 and expected cash flows of ​$21,750 at the end of each year for six years. The discount rate for this project is 9.7 percent. a.  What are the​ project's payback and discounted payback​ periods? b.  What is the​ project's NPV? c.  What is the​ project's PI? d.  What is the​ project's IRR?

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,750,000. The project's expected cash flows are: Year Year 1...

  • Which one of the following statements is correct? Assume cash flows are conventional. Explain how you...

    Which one of the following statements is correct? Assume cash flows are conventional. Explain how you got your answer A. If two projects are mutually exclusive, you should select the project with the shortest payback period. B. The profitability index will be greater than 1.0 when the net present value is negative. C. Projects with conventional cash flows may sometimes have multiple internal rates of return. D. If the required return exceeds IRR, the profitability index will be less than...

  • you are considering a project with an initial cash outlay of $100,000 and expected free cash...

    you are considering a project with an initial cash outlay of $100,000 and expected free cash flow of $50,000 at the end of each year for 3 years. the required rate of return for this project is 10 percent. a. What is the project's conventional payback periods? b. What is the project's discounted payback period? c. what is the project's NPV? d. what is the project's PI? e. what is the project's IRR?

  • Use the following information to answer questions 16 through 20. You are analyzing a proposed project...

    Use the following information to answer questions 16 through 20. You are analyzing a proposed project and have compiled the following information Year Cash flow 0 $145,000 1 $33,400 $ 70,500 $ 82,100 Required payback period 3 years Required return 9.50 percent 16. What is the net present value of the proposed project? a. S6,239.12 b. 58.221.29 c. S6,831.84 d. 58,376.91 17. Should the project be accepted based on the internal rate of return (IRRY? Why or why not? a....

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85.000 and expected free cash flows of ​$20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash...

    (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?

  • Show all work and highlight final answer. Do not answer the question unless you answer all...

    Show all work and highlight final answer. Do not answer the question unless you answer all of them. 4. Which one of the following will decrease the net present value of a project? (a) Increasing the value of each of the project's discounted cash inflows (b) Moving each of the cash inflows forward to a sooner time period (c) Decreasing the required discount rate (d) Increasing the project's initial cost at time zero 5. Which of the following is true...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT