Question

Which one of the following statements is correct? Assume cash flows are conventional. Explain how you...

Which one of the following statements is correct? Assume cash flows are conventional. Explain how you got your answer A. If two projects are mutually exclusive, you should select the project with the shortest payback period. B. The profitability index will be greater than 1.0 when the net present value is negative. C. Projects with conventional cash flows may sometimes have multiple internal rates of return. D. If the required return exceeds IRR, the profitability index will be less than 1.0. E. When the internal rate of return is above than the required return, the net present value is negative.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A. If two projects are mutually exclusive, you should select the project with highest NPV. Hence, A is incorrect.

Net Present value = Present value of Cash Inflows – Present Value of Cash Outflows

Profitability Index = Present Value of Cash Inflows/Initial Investment

Profitability Index is greater than 1, when NPV is Positive and vice versa

Hence, B is incorrect

C. Projects with conventional cash flows will have one IRR, hence c is incorrect

IRR is the return that a project provides. If the required return is less than IRR i.e. project provides higher return than required return, NPV will be positive and Profitability Index will be greater than 1 and vice versa

Hence, the correct statement is D. If the required return exceeds IRR, the profitability index will be less than 1.0.

Add a comment
Know the answer?
Add Answer to:
Which one of the following statements is correct? Assume cash flows are conventional. Explain how you...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company plans to pay an annual dividend of $1.30 a share for two years commencing...

    A company plans to pay an annual dividend of $1.30 a share for two years commencing two years from today. After that time, a constant $2 a share annual dividend is planned indefinitely. Given a required return of 12 percent, what is the current value of this stock? Please explain how you received the answer show your work. A. $14.32 B. $9.65 C. $8.15 D. $5.58 E. $5.25 Which one of the following statements is correct? Assume cash flows are...

  • 18. Which of the following is NOT true about the internal rate of return: A) A...

    18. Which of the following is NOT true about the internal rate of return: A) A good project is one with IRR greater than the required return. B) IRR is the discount rate that results in a zero net present value for the project. C) Crossover rate for two projects is the IRR of the project with the difference of the cash flows of the two projects.. D) For two projects of the same size, IRR will usually choose the...

  • Show all work and highlight final answer. Do not answer the question unless you answer all...

    Show all work and highlight final answer. Do not answer the question unless you answer all of them. 4. Which one of the following will decrease the net present value of a project? (a) Increasing the value of each of the project's discounted cash inflows (b) Moving each of the cash inflows forward to a sooner time period (c) Decreasing the required discount rate (d) Increasing the project's initial cost at time zero 5. Which of the following is true...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 0 -$1,00 Year Project W -$1,000 1 $200 2 $350 $400 $600 Project x -$1,500 $350 $500 $600 $750 Project X Project W If the weighted average cost of capital (WACC) for each...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars Year Project Y Project Z 800 -$1,500 -$1,500 0 $200 $900 1 600 Project Y $400 $600 2 $600 $300 400 $1,000 $200 4 Project Z 200 If the weighted average cost of capital...

  • Which of the following statements are correct? I. A positive net present value signals an accept...

    Which of the following statements are correct? I. A positive net present value signals an accept decision. II. Projects should be accepted when the profitability index is greater than 1. III. A payback period that is less than the required period signals an accept decision. IV. When the internal rate of return exceeds the required return, a project should be accepted.

  • of a project's future cash . .. A project's profitability index is equal to il :...

    of a project's future cash . .. A project's profitability index is equal to il : ratio of the _ nows to the project's !! sh line ... Thi nel present value; initial cash outlay present value; depreciable basis net present value; depreciable basis (c! None of the above Twa mutually exclusive investment proposals have "scale differences" (i.e., the cost of the projects differ). Ranking these projects on the basis of IRR, NPV, and Pl methods give contradictory results. (a)...

  • Consider four projects, which you expect to generate the following cash flows: Year                      Project A      &nbs

    Consider four projects, which you expect to generate the following cash flows: Year                      Project A        Project B                Project C                Project D 0                         (200,000)               (2,000)                 (200,000)               (200,000) 1                          210,000                 18,000                  100,000                   90,000 2                      (100,000 is for project c & d ONLY)    100,000                100,000 3                                                                                      100,000                115,000 , Your required return on all of the investments is 8%. For each project estimate the Payback Period, Internal Rate...

  • Which one of the following indicates that a project should be rejected? O1) Payback period that...

    Which one of the following indicates that a project should be rejected? O1) Payback period that is shorter than the requirement period 2) Negative net present value 3) Internal rate of return that exceeds the required return 4) Profitability index is greater than 1.0 5) Positive net present value

  • Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is...

    Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is 15.7 percent, NPV is -$198, and the payback period is 3.92 years. Which one of the following statements is correct given this information? This project should be accepted based on the internal rate of return. The discount rate used in computing the net present value was less than 15.7 percent. The required rate of return must be greater than 15.7 percent. The discounted payback...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT