Question

Peak Lighting, Inc. Peak Lighting, Inc. develops stages, lighting systems, and special effects for the concert...

Peak Lighting, Inc.

Peak Lighting, Inc. develops stages, lighting systems, and special effects for the concert tours of major musical acts. Recently, they were approached by Bullwhip, a popular band, to develop the stage, lighting, and special effects for its upcoming tour. The project to develop the stage, lighting, and special effects for a concert tour progresses through four major phases. In the first phase, which lasts about a week, Peak develops a sound track for the concert based on the song list the band provides it for the tour. Using the sound crack, Peak employees develop a synchronized lighting and special effects show on a computer that allows them to view an animated stage with the lighting and special effects as the sound track is being played. In the second phase, the materials needed for the stage, lighting, and special effects are ordered from outside suppliers. The lead time for receiving these materials is 4 weeks, and during this period the project team members are assigned to other projects. Once all the materials arrive, the third phase involves constructing the stage with the lighting and special effects. Also, writing the computer code to control the lighting and special effects is done in the third phase. This phase takes 3 weeks. In the final phase, which takes a week, the lighting and special effects are tested and enhanced. The total cost of the Bullwhip project is estimated to be $600,000 of which $400,000 is for the stage, lighting equipment, and special effects, and $200,000 is for labor costs. Eric Page was recently hired as Peak's VP of Operations. All the project managers that oversee the stage and lighting projects report to Eric. Prior to joining Peak Lighting, Eric served as a project manager for a leading management consulting firm for 10 years. Based on extensive project management experience, one of the first things Eric did in his new role as VP was implement a formal project reporting system that would help him monitor the progress of the projects underway. The Bullwhip project had been underway for 5 years, and all the materials had arrived. The project team was now ready to start the third phase of the project and construct the stage with the designed lighting and special effects. In reviewing the most recent progress report for the Bullwhip project and based on his project management experience, Eric became gravely concerned. According to the report, the project had an earned value of $120,000 based on the project manager Jimmy Rush's estimate that 20 percent of the project had been completed. In further studying the report, Eric observed that the planned value and actual costs incurred were both $440,000. Based on his concern, Eric decided to walk down the hall to Jimmy's cubicle and discuss his concerns related to the progress on the project. Eric began: I just reviewed the progress report for the Bullwhip project, and I am very concerned that the project is falling way behind schedule. Based on my review, it appears there are very significant cost and schedule variances. As you know, we have a hard deadline for completing the project as the Bullwhip needs everything fully operational 2 weeks prior to the start of their tour so they can rehearse with it, Jimmy responded: To be perfectly honest, I don't know much about schedule and cost variances, but I do have a great deal of experience managing these projects. Again, I don't know how you calculated the variances you mentioned; but in my view we are exactly where we should be. To this Eric replied: I don't see how you can possibly think the project is on track when it has an earned value of only $120,000 and the planned value by this point in the project is $440,000? And I am equally disturbed you don't understand basic project management concepts such as earned value. Later that day, Jimmy shared his frustration about his new boss with one of the project team members. "Eric really chewed me out today. He questioned my ability to manage a project. I wonder if he even understands the nature of these projects. Does he even get it that two thirds of the project costs are for materials and that these costs are incurred in the early part of the project? Reference. Meredith, J. R., Mantel, S. J., Shafer, S. M., & Sutton, M. M. (2014). Project management in practice. Wiley.

QUESTIONS: 1. Calculate the schedule variance and cost variance for the Bullwhip project?

2. Does Jimmy's point about the material costs have merit? If so, does this have any implications for the way the earned valued is calculated at Peak?

3. Who is right about the status of the project? Eric or Jimmy?

4. What advice, if any, would you offer Eric related to his new role of VP of Operations?

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Peak Lighting, Inc. Peak Lighting, Inc. develops stages, lighting systems, and special effects for the concert...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • •Please help develop an overall delivery Process using the below to be in line with Agile project...

    •Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...

  • Pixel Studio, Inc., is a small company that creates computer-generated animations for films and television. Much...

    Pixel Studio, Inc., is a small company that creates computer-generated animations for films and television. Much of the company’s work consists of short commercials for television, but the company also does realistic computer animations for special effects in movies.          The young founders of the company have become increasingly concerned with the economics of the business—particularly since many competitors have sprung up recently in the local area. To help understand the company’s cost structure, an activity-based costing system has been...

  • Doesn’t Time Fly! It was 7.30 on a Tuesday morning, when John Edwards, general manager of...

    Doesn’t Time Fly! It was 7.30 on a Tuesday morning, when John Edwards, general manager of the Jenkins Company’s main factory, turned on to the M3 to drive to his office in Basingstoke. The journey took about twenty minutes and gave John an opportunity to reflect on the problems of the plant without interruptions. The Jenkins Company ran three printing plants and had nationwide clients for its high-quality colour work. There were about 350 employees, almost half of whom were...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • Why did the Energy Telematics project fail and why was Joel's tram vaught off guard by...

    Why did the Energy Telematics project fail and why was Joel's tram vaught off guard by the hostile reaction of the truck drivers at the Omaha depot? MINI CASE Working Smarter at Continental Furniture International Joel Parsons hurried down the hall to the monthly executive committee meeting doing a mental checklist of all the things he was responsible for: sales analysis-check; mar keting stats-check; quarterly and YTD financials-check; operating statistics-check trends in each of these areas-check. Parsons was right hand...

  • Any reflection or opinion on these two essays? Should Marijuana be legal? 1 answer Within 200...

    Any reflection or opinion on these two essays? Should Marijuana be legal? 1 answer Within 200 words. 1. A Brief History of the Drug War Many currently illegal drugs, such as marijuana, opium, coca, and psychedelics have been used for thousands of years for both medical and spiritual purposes. The Early Stages of Drug Prohibition Why are some drugs legal and other drugs illegal today? It's not based on any scientific assessment of the relative risks of these drugs –...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT