Match the order of the logistics and supportability analysis technique that should be conducted in sequence 1 through 8.
|
System Operational Requirements and the Maintenance concept definition |
Functional Analysis and Requirements Allocation |
LCC Analysis, R&M analysis and Maintenance Task Analysis |
Failure Modes and Critical Effects Analysis |
Reliability Centered Maintenance Analysis |
Preventive Maintenance Program Definition |
Preventive Maintenance Program Evaluation and Continuous Process Improvement |
|
|
This is the first step |
System Operational Requirements and the Maintenance concept definition |
This is the second step in sequence |
Functional Analysis and Requirements Allocation |
This is the third step in sequence |
Failure Modes and Critical Effects Analysis |
This is the fourth step in sequence |
Reliability Centered Maintenance Analysis |
This is the fifth step in sequence |
Preventive Maintenance Program Definition |
This is the sixth step in sequence |
LCC Analysis, R&M analysis and Maintenance Task Analysis |
This is the seventh step in sequence |
Preventive Maintenance Program Evaluation and Continuous Process Improvement |
This is the eight step in process |
Design Analysis and Improved Methods for Conditioning Monitoring |
Question 16 Match the order of the logistics and supportability analysis technique that should be conducted...
First, read the article on "The Delphi Method for Graduate Research." ------ Article is posted below Include each of the following in your answer (if applicable – explain in a paragraph) Research problem: what do you want to solve using Delphi? Sample: who will participate and why? (answer in 5 -10 sentences) Round one questionnaire: include 5 hypothetical questions you would like to ask Discuss: what are possible outcomes of the findings from your study? Hint: this is the conclusion....
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...