Question

Night Tran Construction Company Night Tran Construction Company specializes in building small power plants, mostly for...

Night Tran Construction Company

Night Tran Construction Company specializes in building small power plants, mostly for utility companies. The company was awarded a contract approximately 2 years ago to build such a power plant. The contract stated a project duration of 3 years, after which a 1 percent penalty would be invoked for each additional month of construction. Project records indicate the utility plan is only 50 percent completed and is encountering continuing problems. The owner of Night Tran Company, concerned over the potential losses, investigated the project and found the following: There was an excessive number of engineering design changes; there was a high work rejection rate; and the project was generally understaffed. As a result, she directed the PM to develop a better system of project control and present this method to the board members in 1 week.

Questions

If you were the PM, what characteristics would you be looking for in the new control system? Will a new control system be adequate for the problem? Will it control scope creep? Explain.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution -

It is clear from the above extract that the project suffered from frequent scope changes and also that there were some project expectation differences which led to a lot of delays. The project work estimate was also not upto the mark and hence there were resource issues. As a project manager I would like to have the following characteristics in the new control system -

  • A complete scope definition of the project along with each milestone clearly outlined.
  • A complete list of project metrics and progress of the project.
  • A detailed analysis of the budget and the relevant earned value.
  • A report mechanism which can help communicate the progress of the project to all its stakeholders

This control system will help to keep a track on the progress of the project and also help to ascertain the change in overall metrics if a new task or change in scope is included. This will allow the project manager to decide if the changes are acceptable or not. A clear scope definition provided in the system will allow for lesser rejections and provide clarity to the project team on the expectations of the stakeholders. The dynamic tracking of progress will allow the project manager to ascertain the requirement of resources at each evaluation intervals. Hence a new control system with the above mentioned characteristics can assist in solving the current issues of the project.

Add a comment
Know the answer?
Add Answer to:
Night Tran Construction Company Night Tran Construction Company specializes in building small power plants, mostly for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first...

    Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate,...

  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • Case: Enron: Questionable Accounting Leads to CollapseIntroductionOnce upon a time, there was a gleaming...

    Case: Enron: Questionable Accounting Leads to CollapseIntroductionOnce upon a time, there was a gleaming office tower in Houston, Texas. In front of that gleaming tower was a giant “E,” slowly revolving, flashing in the hot Texas sun. But in 2001, the Enron Corporation, which once ranked among the top Fortune 500 companies, would collapse under a mountain of debt that had been concealed through a complex scheme of off-balance-sheet partnerships. Forced to declare bankruptcy, the energy firm laid off 4,000...

  • CASE 20 Enron: Not Accounting for the Future* INTRODUCTION Once upon a time, there was a...

    CASE 20 Enron: Not Accounting for the Future* INTRODUCTION Once upon a time, there was a gleaming office tower in Houston, Texas. In front of that gleaming tower was a giant "E" slowly revolving, flashing in the hot Texas sun. But in 2001, the Enron Corporation, which once ranked among the top Fortune 500 companies, would collapse under a mountain of debt that had been concealed through a complex scheme of off-balance-sheet partnerships. Forced to declare bankruptcy, the energy firm...

  • I need Summary of this Paper i dont need long summary i need What methodology they used , what is the purpose of this p...

    I need Summary of this Paper i dont need long summary i need What methodology they used , what is the purpose of this paper and some conclusions and contributes of this paper. I need this for my Finishing Project so i need this ASAP please ( IN 1-2-3 HOURS PLEASE !!!) Budgetary Policy and Economic Growth Errol D'Souza The share of capital expenditures in government expenditures has been slipping and the tax reforms have not yet improved the income...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT