Company XYZ uses a standard costing to evaluate operational performance against budget.
The following budget and actual information is presented to you as the accountant:
Budget
Production and sales: 50 000 units
Material usage per unit: 7kg
Price per kg: R10
Labour minutes per unit: 15 min
Total direct labour cost: R2 000 000
Variable costs: R1 500 000
Actual
Production and sales: 47 500 units
Material used: 356 250kg
Cost of material: R3 241 875
Labour minutes: 703 000 min
Total direct labour cost: R1 900 000
Variable costs: R1 400 000
REQUIRED:
Identify and apply an appropriate variance analysis to evaluate direct material, direct labour and variable overheads (where applicable, express answers to one decimal place). Please provide possible reasons for the discrepancies.
Budget | Standard quantity (units) | 50000.0 |
Material usage per unit (kg) | 7.0 | |
Standard price per kg | 10.0 | |
Standard quantity (in kg) | 350000.0 | |
Actual | Production and sales (units) | 47500.0 |
Material used: | 356250.0 | |
Cost of material: | 3241875.0 | |
Material Usage Variance: | Computation | |
Standard quantity (in kg) *Standard price per kg =(350000*10) | 3500000.0 | |
Actual quantity used (in kg)*Standard price per kg =(356250*10) | 3562500.0 | |
Variance | -62500.0 | |
Reason | Variance is adverse as the actual quantity consumed is more than the budgeted quantity |
Material Price Variance: | Computation |
Actual quantity used (in kg)*Standard price per kg =(356250*10) | 3562500.0 |
Actual Cost of material: | 3241875.0 |
Variance | 320625.0 |
Reason | Variance is favourable since the actual price is less than the budgeted price for actual quantity. |
Budget | Total direct labour cost | 2000000.0 |
Actual | Total direct labour cost | 1900000.0 |
Labour Cost Variance | 100000.0 | |
Reason | Variance is favourable since the actual cost is less than the budgeted cost of labour. |
Budget | Variable costs: | 1500000.0 |
Actual | Variable costs: | 1400000.0 |
Variable Cost Variance | 100000.0 | |
Reason | Variance is favourable since the actual cost is less than the budgeted cost for variable overhead. |
Company XYZ uses a standard costing to evaluate operational performance against budget. The following budget and...
QUESTION 1 (3C 1.1 INFORMATION: Britelite Manufacturers produces a product which has the following standard costs: Material A: 3 kilograms at R20 per kilogram Material B:5 kilograms at R15 per kilogram Direct labour: 8 hours at R10 per hour Fixed overheads: R120 000 Budgeted production: 9000 units Actual results for February 2019 were as follows: Material A: 32 500 kg at R22 per kilogram Material B: 54 000 kg at R14 per kilogram Direct labour: 88 000 hours at R12...
The monthly budget of Steelworks, manufacturers of specialist cabinets, was prepared on the following specification:Production and sales30 000 unitsSelling priceR80 per unitDirect materials input5 kg per unit at a cost of R1,20 per kgDirect labour input2 hours per unit at a rate of R4 per hourVariable overheadR2 per direct labour hourFixed overheadR110 000 per monthThe following actual results were recorded for the month of August:Stock of finished goods at start of month8 000 unitsSales40 000 unitsProduction42 800 unitsStock of finished...
Hilda Ltd uses the standard costing system. The standards for Product Z100 are as follows: Material 4 kilograms at R2.50 per kilogram Labour 4 hours at R100 per hour Variable overheads R40 per labour hour Fixed overheads R48 000 Normal production 24 000 units per month Actual production for the month of November 2016 on Product Z100 is: Material 81 000 kilograms used at R2.50 per kg Labour 78 000 hours worked at R96 per hour Variable overheads R44 per...
Question 1 (40 marks) Magnate Ltd is a manufacturing company which produces a fixed budget for planning purposes. Set out below is the monthly fixed budget of production costs, together with the actual results observed for the month of November 2019. Budget Actual Units produced 5,000 5,500 £ £ Cost Direct material 20,000 22,764 Direct labour 60,000 75,900 Variable Production overhead 14,000 14,950 Fixed Production overhead 10,000 9,000 Depreciation 4,000 4,000 In preparing the flexed budget, the following standards were...
INFORMATION The following information is available to determine the budget requirements of Medico Limited for January 2021: 1. Projected sales of Product Med for January and February 2021: January February 15 000 units at R30 each 12 000 units at R32 each 2. The policy of Medico Limited is to maintain a closing inventory equal to 40% of the budgeted sales of the following month. 3. Two (2) labour hours are required to produce one unit of Product Med and...
Moon (Ltd) manufacture specially treated garden benches. The following information was extracted from the budget for the year ended 29 February 2016: Estimated sales for the financial year 2 000 units Selling price per garden bench R450 Variable production cost per garden bench: - Direct material - Direct labour - Overheads R135 R90 R45 Fixed production overheads R127 500 Selling and administrative expenses: - Salary of sales manager for the year - Sales commission R75 000 10% of sales Required:...
Tripcurl Surfboards is considering using variances calculated in parts 1) and 2) to evaluate the performance of its materials purchasing manager and production manager. Discuss any two limitations which the business should be aware of when using variances to evaluate manager performance Tripcurl Surfboards manufactures fiberglass surfboards. The standard cost of direct materials and direct manufacturing labour is.100 dollars per board. This includes 20 pounds of direct materials, at the budget prices of $2 per pound and 5hours of direct...
. Q1: The following profit reconciliation statement summari zes t ance of one of SEWs products for March. Budgeted profit Sales volume variance Standard profit on actual sales Selling price variance 4 250 85DA 3 400 4000А (600) Adverse Favourable Cost variances: 1 000 Direct material price Direct material usage Direct labour rate Direct labour efficiency Variable overhead expenditure Variable overhead efficiency Fixed overhead expenditure Fixed overhead volume Actual profit 150 200 150 600 75 2 500 150 1175 36502475F...
Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. calculate the following variances: Material Price Variance Materials Quantity Variance Total Materials Variance...
3. The company manufactures two products - A and B. Item name Direct material costs (euro per unit) Direct labor cost (euro per hour) Variable overheads Labour time, hours per unit Material B for production, kg Sales price Demand for the products (in units) 24 1800 28 5200 Company can use direct labor time, 28 000 hours and material B 32 000 kg. What is the product production plan which will ensure maximum profit, assuming that the fixed cost per...