Question

. Q1: The following profit reconciliation statement summari zes t ance of one of SEWs products for March. Budgeted profit Sales volume variance Standard profit on actual sales Selling price variance 4 250 85DA 3 400 4000А (600) Adverse Favourable Cost variances: 1 000 Direct material price Direct material usage Direct labour rate Direct labour efficiency Variable overhead expenditure Variable overhead efficiency Fixed overhead expenditure Fixed overhead volume Actual profit 150 200 150 600 75 2 500 150 1175 36502475F 1875
datą The budget for the same period Sales volume Sales revenue Production volume Direct materials purchased Direct materials used Direct material cost 2 4 500 Direct labour hours contained the following 1 500 units £20 000 1 500 unit 750kg 750kg 1 125 Direct labour cost 24 500 Variable overhead costS 12 250 Fixed overhead cost 4 500
Additional information: stocks of raw materials and finished goods are valued at standard cost- during the month the actual number of units produced was 1550; the actual sales revenue was £12 000; the direct materials purchased were 1000kg
Required: . (a) Calculate () the actual sales volume: -950 x-00 (ii) the actual quantity of materials used:, (ii) the actual direct material cost, 6xlooo (iv) the actual direct labour hours; 150-( (v) the actual direct labour cost, (vi) the actual variable overhead cost;-600 (vii) the actual fixed overhead cost. 45DD- ー120ニー
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: (i) A fixed overhead volume variance only occurs with an absorption costing system. The question indicates that a volume variance has been reported. Therefore the company must operate an absorption costing system and report the sales volume variance in terms of profit margins, rather than contribution margins. Budgeted profit margin-budgeted profit /budgeted volume -£425011500 units £2.83 Adverse sales volume variance in units = £850,£2.83-300 units Therefore actual sales volume was 300 units below budgeted sales volume Actual sales volume 1500 units 300 units 1200 units (ii) Standard quantity of material used per units of output-budgeted usage / budgeted production -750 kg 1500 units 0.50 kg Standard price -budgeted material cost/budgeted usage £4500/750 kg - £6 Material usage variance (standard quantity actual quantity) standard price £150A [(550 x 0.5 kg) - AQ)] £6 £150 E4650 - 6AQ 6AQ-14,800 Actual quantity used - 800 kg (iii) Material price variance (standard price- actual price) x actual purchases £1,000F = (£6-actual price) x 1 000 kg £1,000F£6 000 1,000AP 1,000AP- £5 000 AP = £5 per kg Actual material cost- 1 000 kg x £S £5 000 Created by Universal Document Converter(iv) Standard hours per unit of output Budgeted hours/Budgeted output = 1 1 25/1 500 -0,75 hours Standard wage rate budgeted

Add a comment
Know the answer?
Add Answer to:
. Q1: The following profit reconciliation statement summari zes t ance of one of SEWs products...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A manufacturer had the following information:        Budget Actual Units produced        10,000    11,050 Materials used...

    A manufacturer had the following information:        Budget Actual Units produced        10,000    11,050 Materials used in production             400 kg             ? Material Costs $      8,000             ? Direct Labour (Hours)       35,000 hrs     41,010 hrs Direct Labour Costs $ 385,000 $450,951 Variable Overhead Costs $ 350,000 $411,441 Fixed Overhead Costs $ 160,000 $136,358 Other Information Overhead is Allocated on Direct Labour Hours During the year, 602 kg of materials were purchased for $12,000 Beginning Direct Material Inventory:...

  • The monthly budget of Steelworks, manufacturers of specialist cabinets, was prepared on the following specification:

    The monthly budget of Steelworks, manufacturers of specialist cabinets, was prepared on the following specification:Production and sales30 000 unitsSelling priceR80 per unitDirect materials input5 kg per unit at a cost of R1,20 per kgDirect labour input2 hours per unit at a rate of R4 per hourVariable overheadR2 per direct labour hourFixed overheadR110 000 per monthThe following actual results were recorded for the month of August:Stock of finished goods at start of month8 000 unitsSales40 000 unitsProduction42 800 unitsStock of finished...

  • sol th Question 4 (10 marks) The following is the standard cost card for X Company's...

    sol th Question 4 (10 marks) The following is the standard cost card for X Company's only product: Direct materials, 4 metres at $4.00 Direct labour, 1.5 hours at $10.00 Variable overhead, 1.5 hours at $3.00 Fixed overhead, 1.5 hours at $7.00 Standard cost per unit $16.00 $15.00 $4.50 $10.50 $46.00 The company manufactured and sold 18 000 units of product during the year. A total of 70,200 metres of material was purchased durine the vear at cost of $4.20...

  • You have been given the following list of variances for the Pennadi Company:         Direct...

    You have been given the following list of variances for the Pennadi Company:         Direct materials price variance $ 16,800 U   Direct materials quantity variance 12,000 U   Direct labour rate variance 16,270 F   Direct labour efficiency variance 27,000 U   Variable overhead spending variance 3,120 U   Variable overhead efficiency variance 6,000 U   Fixed overhead budget variance 5,000 U Fixed overhead volume variance 53,250 F You have also been given the following information:         Actual units produced 25,000   Budgeted units...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. calculate the following variances: Material Price Variance Materials Quantity Variance Total Materials Variance...

  • Question 7 (12 marks) Bright Electric Company Limited manufactures electric table lamps The standard cost specification...

    Question 7 (12 marks) Bright Electric Company Limited manufactures electric table lamps The standard cost specification sheet of the company shows the following information related to its standard costs that have been set for its new model called Slim Line Elegance as: $14.00 $12.00 Direct materials (1 kg) Direct labour (2 hours) Overhead: Fixed - $1.10 per direct labour hour Variable - $1.30 per direct labour hour $2.20 $ 30.80 Actual production and cost information for December 2018 is as...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. Solve for: Variable Overhead Spending Variance Variable Overhead Efficiency Variance Variable Overhead Total...

  • Direct Material Variances Goldman, Inc. is a manufacturer of lead crystal glasses. The standard direct materials quantit...

    Direct Material Variances Goldman, Inc. is a manufacturer of lead crystal glasses. The standard direct materials quantity is 0.7 pounds per glass at the cost of $0.35 per pound. The actual result for one month’s production of 6,950 glasses was 1.3 pounds per glass, at the cost of $0.45 per pound. Calculate the direct materials cost variance and the direct materials efficiency variance. Direct Labour Variances Goldman, Inc. manufactures lead crystal glasses. The standard direct labor time is 0.5 hours...

  • Required information Use the following information for the Problems below. The following information applies to the q...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $5. 10 per Ib.) Direct labor (4 hrs. @$15 per hr.) Factory overhead-variable (4 hrs $6 per hr.) Factory overhead- fixed (4 hrs. Q $11 per hr. ) 153, 00 60, 00 24. 00 44, 00 281. 00 Total standard cost The predetermined overhead rate...

  • QUESTION 1: IDE company manufactures and sales one product. There is no opening or closing inventories...

    QUESTION 1: IDE company manufactures and sales one product. There is no opening or closing inventories and work in progress is negligible. The company operates a standard costing system and analysis of variances and reports are prepared every month for management's planning control and decision making. The below product information is given; Standard selling price K32 Standard contribution K13.4 Variable overheads 2hrs@30ngwee/hr k0.60 Direct wages 2hrs@K8/hr K16 Direct Materials 0.5kgs @K4/kg K2 Further information is given as follows: Variable overheads...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT