Question

We sometimes have to choose between the highest NPV and IRR; will we not always get...

We sometimes have to choose between the highest NPV and IRR; will we not always get the same decision from both of these models?

A company should accept a project if the IRR is greater than the WACC. Why will that always help maximize shareholder wealth?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer-  

No we does not get the same decisions when we use NPV and IRR.

The advantage of NPV method is that it is a direct measure of the expected increase in the value of the firm, however it does not take into consideration the size of the project.
The advantage of IRR is that it measures the profitability as a percentage which gives the return on each fdollar invested, however the disadvantage of IRR is that a project has multiple IRRsor no IRR.


If Project X has a higher IRR than Project Y, then Project X must also have a higher NPV.

For mutually exclusive projects if the NPV method and the IRR method give conflicting rankings one should use the NPV to select the project.

Answer-

The cost of capital (WACC)  is the minimum return required by shareholders.

When firms undertake projects where the IRR is equal to the WACC then the NPV is equal to zero and therefore it does not add any value to the firm.


When the IRR is greater than WACC the NPV is positive and therefore it adds value to the firm and increases or maximizes the shareholders wealth.  

If a project's NPV is less than zero, then its IRR must be less than the WACC.

Therefore a company should accept the project if IRR is greater than WACC.

Add a comment
Know the answer?
Add Answer to:
We sometimes have to choose between the highest NPV and IRR; will we not always get...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following is true about comparing NPV and IRR rule? (a) NPV is strictly...

    Which of the following is true about comparing NPV and IRR rule? (a) NPV is strictly better than IRR so no CFO or CEO in the real world actually uses IRR. (b) No matter what the cash flow patterns are, with unlimited resources and same project lives, we can always choose the one with highest NPV among mutually exclusive projects. (c)When mutually exclusive projects have different lives, we should use IRR rather than NPV rule. (d) NPV rule guarantees correct...

  • First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR,...

    First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR, MIRR, required rate of return Fourth Blank: IRR method, NPV method 6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....

  • 8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the...

    8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation (BRC). Both projects require an annual return of 14 percent. Main Page Year Deepwater Fishing New Submarine Ride Incremental (Ride-Fishing) 0 $(850,000.00) $(1,650,000.00) $(800,000.00) 1 $320,000.00 $810,000.00 $490,000.00 2 $470,000.00 $750,000.00 $280,000.00 3 $410,000.00 $690,000.00 $280,000.00 Discount Rate IRR NPV As a financial analyst for BRC, you are asked the following questions: a. If your decision rule is to accept the...

  • why is for the calculation of NPV various methods are used? like sometimes it is like...

    why is for the calculation of NPV various methods are used? like sometimes it is like the NPV of a project is determined by dividing the given cash flows for the year by given WACC whereas on the contrary, NPV is calculated by multiplying the given cash flows with present value factors? this sounds a bit crazy as well but i am confused. so can you please explain this? aptal budgeting and cash flow estimation Internal Rate of Return (IRR)...

  • Which of the following statement of IRR analysis is TRUE? A. A project can only have...

    Which of the following statement of IRR analysis is TRUE? A. A project can only have one IRR. B. If a project has two IRR, then we will accept the project when the required rate of return is smaller than both IRR. C. When evaluating mutually exclusive projects, the project with highest IRR also has the highest NPV. D. When calculating IRR of a project, we need both cash flows and required rate of return of the project. E. For...

  • 9. What is the intuition behind the IRR rule? Under what conditions will the IRR rule...

    9. What is the intuition behind the IRR rule? Under what conditions will the IRR rule and the NPV rule give the same accept/reject decision? 10. Explain what is meant by ‘mutually exclusive projects’ and why it is generally a bad idea to use IRR to choose between mutually exclusive projects? 11. Using an example of each, explain sunk costs and opportunity costs. Which of these costs should be included in incremental cash flows and which should be excluded? 12....

  • NPV versus IRR Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow...

    NPV versus IRR Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$77,500 -$77,500 43,000 21,500 29,000 28,000 23,000 34,000 21,000 41,000 a. What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will you choose...

  • 12. NPV versus IRR (LO1, 5) Parkallen Inc. has identified the following two mutually exclusive projects:...

    12. NPV versus IRR (LO1, 5) Parkallen Inc. has identified the following two mutually exclusive projects: m Cash Flow (A) Cash Flow (B) Year -$29,000 14,400 -$29000 0 1 4,300 2 12,300 q.800 4.200 15,200 4 5,100 16,800 Click here for a description of Table: Questions and Problems 12. a. What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return...

  • Question 22 (3 points) If a layman asks you to explain the relationship between NPV and...

    Question 22 (3 points) If a layman asks you to explain the relationship between NPV and IRR, you could answer correctly using this statement: both approaches always provide the same ranking of alternative investment projects if the NPV of a project is negative, the IRR must be greater than the cost of capital the IRR of a project is equal to the firm's cost of capital if the NPV of a project is $0. none of the above

  • 4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...

    4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT