Question

Required information [The following information applies to the questions displayed below.] Fiber Technology, Inc., manufactures glass...

Required information

[The following information applies to the questions displayed below.]

Fiber Technology, Inc., manufactures glass fibers used in the communications industry. The company's materials and parts manager is currently revising the inventory policy for XL-20, one of the chemicals used in the production process. The chemical is purchased in 10-pound canisters for $96 each. The firm uses 4,000 canisters per year. The controller estimates that it costs $151 to place and receive a typical order of XL-20. The annual cost of storing XL-20 is $4.10 per canister.

Required:

  1. Use the EOQ formula to determine the optimal order quantity.

  2. What is the total annual cost of ordering and storing XL-20 at the economic order quantity?

  3. How many orders will be placed per year?

  4. Fiber Technology’s controller, Jay Turnbull, recently attended a seminar on JIT purchasing. Afterward he analyzed the cost of storing XL-20, including the costs of wasted space and inefficiency. He was shocked when he concluded that the real annual holding cost was $20.20 per canister. Turnbull then met with Doug Kaplan, Fiber Technology’s purchasing manager. Together they contacted Reno Industries, the supplier of XL-20, about a JIT purchasing arrangement. After some discussion and negotiation, Kaplan concluded that the cost of placing an order for XL-20 could be reduced to just $21. Using these new cost estimates, Turnbull computed the new EOQ for XL-20.

  1. a. Use the equation approach to compute the new EOQ.

  2. b. How many orders will be placed per year?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

EOQ :-

   √(2)[(annual requirement)(Cost per order)] / annual carrying cost per unit

√(2)(4000)($151) / $4.10

√294634.15

= 542.80 or 543

Total Annual cost of ordering & storing :-

[(annual requirement/EOQ) * Cost per order] + [(EOQ/2) * annual carrying cost per unit]

[(4000/543) * $151] + [(543/2) * $4.10

=$2226

Orders placed =   Orders = Annual requirements/EOQ

    = 4000/543 = 7.37 or 8 orders

After new Estimation (JIT)

(a) EOQ:-

   √(2)[(annual requirement)(Cost per order)] / annual carrying cost per unit

√(2)(4000)($21) / $20.20

91.20 or 92

(b) How many orders?

   Orders = Annual requirements/EOQ

    = 4000/92 = 43.47 or 44 orders

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] Fiber Technology, Inc., manufactures glass...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Fiber technology Inc., manufactures glass fibers used in the communications industry, The company's materials and parts...

    Fiber technology Inc., manufactures glass fibers used in the communications industry, The company's materials and parts manager is currently revising the inventory policy for XL-20, one of the chemicals used in the production process. The chemical is purchased in 10 pound canisters for $110 each. The firm uses 5,400 canisters per year. The controller estimates that it costs $165 to place and recieve a typical order of XL-20. The annual cost of storing XL-20 is $5.50 per canister. 2. Use...

  • EOQ

    Bundaberg Glass Company is a distributor of car windscreens. The windscreens are manufactured in Japan and shipped to Bundaberg. Management is expecting an annual demand of 10 800 windscreens. The purchase price of each windscreen is $400. Other costs associated with ordering and maintaining an inventory of these windscreens are shown below. §  The ordering costs incurred in the purchase order department for placing and processing orders for the past three years are shown below. Year                Orders placed and processed              Total processing...

  • Required information [The following information applies to the questions displayed below.] Kinnear Plastics manufactures various components...

    Required information [The following information applies to the questions displayed below.] Kinnear Plastics manufactures various components for the aircraft and marine industry. Kinnear buys plastic from two vendors: Tappan Corporation and Hill Enterprises. Kinnear chooses the vendor based on price. Once the plastic is received, it is inspected to ensure that it is suitable for production. Plastic that is deemed unsuitable is disposed of. The controller at Kinnear collected the following information on purchases for the past year: Tappan Hill...

  • [The following information applies to the questions displayed below.] Kinnear Plastics manufactures various components for the...

    [The following information applies to the questions displayed below.] Kinnear Plastics manufactures various components for the aircraft and marine industry. Kinnear buys plastic from two vendors: Tappan Corporation and Hill Enterprises. Kinnear chooses the vendor based on price. Once the plastic is received, it is inspected to ensure that it is suitable for production. Plastic that is deemed unsuitable is disposed of The controller at Kinnear collected the following information on purchases for the past year: Таppan 4,500 Hill Total...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • Required information The following information applies to the questions displayed below.] Kitchen King's Toledo plant manufactures...

    Required information The following information applies to the questions displayed below.] Kitchen King's Toledo plant manufactures three product lines, all multi-burner, ceramic cook tops. The plant's three product models are the Regular (REG), the Advanced (ADV), and the Gourmet (GMT). Until recently, the plant used a job- order product-costing system, with manufacturing overhead applied on the basis of direct-labor hours. The following table displays the basic data upon which the traditional costing system was based REG ADV GMT Planned annual...

  • Check my work Required information [The following information applies to the questions displayed below.] Rusties Company...

    Check my work Required information [The following information applies to the questions displayed below.] Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 28,050 $ 2,100 $ 4,420 $...

  • Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of ordere Number of receipts Number of relays Machine-hours Expected Overhead Coat $ 60,000 $ 16,800 $ 15,000 $ 35,200 $400,000 Expected...

  • Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 42,500 $ 5,600 $ 10,000 $ 14,400 $245,000 Expected...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT