Solution :
What is the standard direct labor rate per hour?
Particulars | Amount |
Standard variable manufacturing overhead cost for march | $1456 |
Standard variable manufacturing overhead rate per direct labor hour | $2 |
Standard direct labor hours for march |
=1456/2 = $ 728 |
Standard direct labor rate per hour |
=$ 7280/$728 = $ 10 |
What was the labor rate variance for march? The labor efficiency variance?
Particulars | Amount | Amount |
Actual Cost per unit of back pack production |
=(15,600+7280+1456)/(520)-(0.20) |
$ 46.6 |
Total Number of produced Back packs | 520 | |
Total Actual cost of production | $ 24,232 | |
Less: Actual cost of materials | 14,325 | |
Actual cost of manufacturing Overhead | 1717 |
=14325+1717 = $ 16042 |
Actual cost of Direct Labor |
=24,232-16042 = $ 8,190 |
|
Direct labor Rate | = (780*$10)-$ 8190 | = -$ 390 |
Labor efficiency varaince | = 7280-8190 | = -$ 910 |
What was the variable overhead rate variance for march?The variable overhead efficiency variance?
Variable overhead rate variance=(Actual Hour*Actual Rate)-(Actual Hour of input*Standard Rate)
=(1717-(780*2))
= $ 157
Variable overhead rate variance = $ 157 |
Variable overhead efficiency variance ( Actual Hour * Standard rate)-(Standard Hour * Standard R ate)
=(780 * 2)-1456
=1560-1456
= $ 104
Prepare a standard cost card for one backpack?
Particulars | SR | SC of Back pack | Amount |
Direct Materials |
=($15600/520)/$6 = 5 Yards |
$ 6 |
= 5 * $ 6 = $ 30 |
Direct labor |
= $ 728/520 = $ 1.4 |
$10 | $14 |
Variable Manufacturing Overhead | $ 1.4 | $ 2 |
= $ 1.4 * $ 2 = $ 2.8 |
Total Standard cost per unit of Backpack |
= $ 30+$ 14+$ 2.8 = $ 46.8 |
Problem 10-16 Comprehensive Variance Analysis Lo10-1, LO10-2, LO10-3] Highland Company produces a...
Problem 10-16 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate $6.00 per yard Standard Cost Direct materials Direct labor ? per direct labor 2 hour nin. nn. $ Variable manufacturing overhead Total standard cost per unit Overhead is applied to production on the basis of direct labor-hours. During March, 800 backpacks...
Problem 10-16 (Algo) Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard varlable costs relating to a single backpack are given below: Standard Quantity Standard Price Standard or Hours or Rate Cost $4.00 per yard Direct materials Direct labor per direct 2 labor-hour Variable manufacturing overhead Total standard cost per unit Overhead is applied to production on the basis of direct labor-hours. During March, 700 backpacks were manufactured and sold....
Problem 10-16 (Algo) Comprehensive Variance Analysis (L010-1, LO10-2, LO10-3) Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below. Standard Quantity or Hours Standard Price or Rate Standard Cost $6.00 per yard $? Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit $ per direct 2 labor-hour Overhead is applied to production on the basis of direct labor-hours. During March, 400 backpacks were manufactured...
Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity Standard Price Standard or Rate Direct materials Direct labor $6.00 per yard per direct labor. Variable manufacturing overhead Total standard cost per unit Overhead is applied to production on the basis of direct labor-hours. During March, 520 backpacks were manufactured and sold. Selected information relating to the month's production is given below. Materials Direct Labor...
Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below:Standard Quantity or HoursStandard Price or RateStandard CostDirect materials?$6.00 per yard$?Direct labor???Variable manufacturing overhead?$2 per direct labor-hour?Total standard cost$?Overhead is applied to production on the basis of direct labor-hours. During March, 530 backpacks were manufactured and sold. Selected information relating to the month's production is given below: Materials UsedDirect LaborVariable Manufacturing OverheadTotal standard cost allowed ^(**)$15,900$7,420$1,484Actual costs incurred$13,750?$1,708Materials price variance?Materials...
Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Qtity Standard Price Standard or Rate $4.00 per yard or Hours Cost S? Direct materials Direct labor Variable manufacturing overhead $2 per direct labor-hour Total standard cost Overhead is applied to production on the basis of direct labor-hours. During March, 490 backpacks were manufactured and sold. Selected information relating to the month's production is given below:...
I only need 4, 6, 7, & 8 Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate $6.00 per yard Standard Cost $ ? Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit $ 2 per direct labor-hour $? Overhead is applied to production on the basis of direct labor-hours. During March, 530 backpacks were...
Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below Standard Price or Rato standard Cost standard Quantity or Hours Direct materials Direct labor $4.58 per yard per direct labor Variable manufacturing overhead Total standard cost per unit $2 hour Overhesd is applied to production on the basis of direct labor-hours. During March, 530 backpscks were manufactured and sold Selected information relating to the month's production is...
only 5,6,7&8 please Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate $6.00 per yard $ 2 per direct labor-hour Standard Cost $ ? Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit Overhead is applied to production on the basis of direct labor-hours. During March, 760 backpacks were manufactured and sold. Selected information relating...
please answer 1 to 8 thank you! Saved Help Save & Exis Chec Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3) Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate $6.00 per yard Standard Direct materials Direct labor Cost $7 7 per direct 2 labor-hour Variable manufacturing overhead Total standard cost per unit ? $7 Overhead is applied...