Design the wood wall formworkfor a 14’ - 10” (14.8 ft) high wall to be placed at the rate of pour of 4 ft per hour, internally vibrated.
Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75oF. The unit weight of concrete is 150 lbs/ft3with a slump of 3 inches.
The forms will have continuing reuse. Assume that deflection is limited to l/360 of the span. All lumbers are S4S. Use form grade plywood sheathing ¾ inch thick in 4x8 - ft. sheets. Use 4x4 studs and double 2x6 walers. 4300 lb coil ties are to be used.
Framing lumber is No. 2 Douglas Fir-Larch. Fb = 900 psi, Fc= 625 psi (perpendicular to grain), Fc = 1650 psi (parallel to grain), Fv=180 psi, E=1,600,000 psi
Provide the following:
Show all equations, tables used, and other details of your work.
Design the wood wall formworkfor a 14’ - 10” (14.8 ft) high wall to be placed at the rate of pour...
Design the wood wall formworkfor a 14’ - 10” (14.8 ft) high wall to be placed at the rate of pour of 4 ft per hour, internally vibrated. Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75oF. The unit weight of concrete is 150 lbs/ft3with a slump of 3 inches. The forms will have continuing reuse. Assume that deflection is limited to l/360 of the...
4) Design a vertical wall by providing adequate spacing of studs and wales and identifying which spacing governs between the bending, deflection, rolling shear. Also design for the maximum spacing of the ties and the bearing. (note you need more than 1 set of wales, they are to be spaced equally) Form grade plywood sheathing 3/4 inch. thick is available in 4x8 ft. sheets, and 4500-1b coil ties are on hand. Framing lumber of No. 2 Douglas Fir-Larch is to...
using job built wood forms, Use PROVIDED , refer to Sketch #3 which shows a wall forming system following the following design properties and THE ACI CHARTS Maximum concrete pressure 1,050 psf For sheeting assume 1" plywood used in the stro Studs are 2X6's S4S (smooth all 4 sides) Walers are double 4x8's S4S stgacing between studs f the above mentioned 1" plywood is used in the strong direction for sheeting. (5 pts.) 4. Ignore the answer obtained in problem...