using job built wood forms, Use PROVIDED , refer to Sketch #3 which shows a wall...
Design the wood wall formworkfor a 14’ - 10” (14.8 ft) high wall to be placed at the rate of pour of 4 ft per hour, internally vibrated. Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75oF. The unit weight of concrete is 150 lbs/ft3with a slump of 3 inches. The forms will have continuing reuse. Assume that deflection is limited to l/360 of the...
Design the wood wall formworkfor a 14’ - 10” (14.8 ft) high wall to be placed at the rate of pour of 4 ft per hour, internally vibrated. Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75oF. The unit weight of concrete is 150 lbs/ft3with a slump of 3 inches. The forms will have continuing reuse. Assume that deflection is limited to l/360 of the...