Question

Question #2 (15 Points) The result of a detailed study of setup procedure on a molding machine is shown in Table 1 below. The

product is S1.5. If the batch size is 49 units and product is sold for $9.6 per unit, determine 1)- actual production cycle t

only question 3

Question #2 (15 Points) The result of a detailed study of setup procedure on a molding machine is shown in Table 1 below. The setup involved removing an old die and installing a new one. Tahle I InternalTime Performed by External?(min) Step# Setup 1 Check in at operation, go to die storage 2 Transfer new die 3 Remove old die 10 Setup person 16 Setup person 20 Setup person 20 Setup persorn 30 Operator 24 Setup person 40 Setup person Return old die to storage 5 Get new material Attach new die 7 Adjust machine What you need to do: 1)- define internal and external setup elements (1-2 line each. Classify the elements into internal and external setup operation (fill the corresponding column) 2)-Determine the % of current setup time that you classify as internal, what the minimum (ideal) setup time? 3)- Suppose we modify the procedure and in the new procedure step 5 takes 45 minutes and step 6 takes 27 minutes. How long should the setup procedure take Question 3 (10 points) in Question #2 , suppose at present condition, the operator and the setup person are paid $15 and $20 per hour respectively. The production rate is 4 units per hour and material cost per unit of
product is S1.5. If the batch size is 49 units and product is sold for $9.6 per unit, determine 1)- actual production cycle time, 2)-the resulting % profit PART I. Prohlems
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answen: Fromナhe guen equation To -find dhe production yde time 4 urub = 1 hout Then, 1 unit - 4 49 unitsx 49 4- 49 unit ะ 12.

Add a comment
Know the answer?
Add Answer to:
Question #2 (15 Points) The result of a detailed study of setup procedure on a molding machine is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. Changeover of fixtures on a machine takes 35 minutes. Following the changeover, an aver- ed be...

    5. Changeover of fixtures on a machine takes 35 minutes. Following the changeover, an aver- ed before the correct setting is achieved. For ch part the processing time is two minutes and the material cost is $1.50. The labor cost for a skilled setup person to do the changeover and adjustment is $15.50 per hour. The labor cost of the machine operator is $10.50 per hour. Currently, the part is produced in batches of 50 units. Suppose the setup procedure...

  • Pareto Chart and A report summarizing the costs, percent of total, and percent of sales by appraisal, prevention, internal failure, and external failure cost of quality categories.Cost of Quality Re...

    Pareto Chart and A report summarizing the costs, percent of total, and percent of sales by appraisal, prevention, internal failure, and external failure cost of quality categories.Cost of Quality Report for a Manufacturing Company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an The study of employee effort and other business records to determine the cost of activities.activity analysis to gain a better...

  • please include all the information and step by step procedure. #2: Gene Translation How many ribosomes...

    please include all the information and step by step procedure. #2: Gene Translation How many ribosomes are actively synthesizing proteins at any instant in an E. coli cell growing with a doubling time of 45-minutes? Use the following assumptions in your calculations- a. The birth size (size just after mitosis is complete) of E. coli is 1 micron in diameter and 2 microns in length. b. Water content of the cell is 85%. 50% of the dry cell mass is...

  • Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly o...

    Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly operation, a number。individuals are esponsible for assenting electronic components into pn te i ut boards. Each operator s es ons le r so den g e net erdg to a given set of instructions. Operators work on batches of s0 printed dircuit boards. Each board requires 4 minutes of board assembly time. After each...

  • Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...

    Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...

  • Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...

    Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...

  • Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly,...

    Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator...

  • Question 2 A fast-food franchise is considering operating a drive-up window food-service operatio...

    Question 2 A fast-food franchise is considering operating a drive-up window food-service operation. Assume that customer arrivals follow a Poisson probability distribution, with an arrival rate of 24 cars per hour, and that service times follow an exponential probability distribution. Arriving customers place orders at an intercom station at the back of the parking lot and then drive to the service window to pay for and receive their orders. The following three service alternatives are being considered: A single-channel operation...

  • 1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e.,...

    1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e., workers must multitask and perform multiple activities for every flow unit.) 3. The resource that limits hourly production is not the same resource that limits the process lead-time. From 2002 to 2009, Honda’s 1800cc cruiser-style motorcycle, the VTX1800, was assembled in Marysville, Ohio from four major subassemblies. The following is a simplified explanation of the assembly process. All resources are indicated in bold.   •...

  • Question Help The table below provides the parameters for a new current state vake stream map...

    Question Help The table below provides the parameters for a new current state vake stream map for the family traine e Jensen Bearings infirm described in the chapter. This table depicts the value stream atter Kline Steel agrees to condaily orders for steel sheels and also agrees to deliver on a daily basis Calculate each component of the new value stream's reduced lead me Jensen Bearings operates 5 days per week Click the icon to view the data from the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT