Question

One internal carpentry crew One external carpentry crew One plumbing crew They are working concur...

One internal carpentry crew One external carpentry crew One plumbing crew

They are working concurrently on the jobsite to perform the following construction activities with the estimated durations provided below.

§ Construction activity

Days § Frame exterior Stud Walls 4
§ Place sheathing on exterior walls 1
§ Frame interior stud walls 2
§ Install exterior wall-mounted plumbing fixtures 5

What is the minimum number of workdays (effective days)?

A 1

B 9

C 11

D 12

I picked 12 because its asking workable days, why is it not 12?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans: Minimum number of workdays are 9 days .

Because when we take each activity Framing take 4 days , while framing we can use early start condition i.e., when one worker framing the wall then the other will sheathing to that wall. So both activities simultaneously take only 4 days , and once the framing completed then Fixing of plumbing fixtures take 5 days then there we can done internal wall framing. By this the effective days that can require to complete this activities is 9 days.

And when it comes to question why its not 12 days , by the early start and early finish we can comlete the above work in maximun of 9 days. So there is no need of considering each activity period separately.

Add a comment
Know the answer?
Add Answer to:
One internal carpentry crew One external carpentry crew One plumbing crew They are working concur...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was...

    can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...

  • summarizr the followung info and write them in your own words and break them into different...

    summarizr the followung info and write them in your own words and break them into different key points.   6.5 Metering Chamber: 6.5.1 The minimum size of the metering box is governed by the metering area required to obtain a representative test area for the specimen (see 7.2) and for maintenance of reasonable test accuracy. For example, for specimens incorporating air spaces or stud spaces, the metering area shall span an integral number of spaces (see 5.5). The depth of...

  • summatize the following info and break them into differeng key points. write them in yojr own...

    summatize the following info and break them into differeng key points. write them in yojr own words   apartus 6.1 Introduction—The design of a successful hot box appa- ratus is influenced by many factors. Before beginning the design of an apparatus meeting this standard, the designer shall review the discussion on the limitations and accuracy, Section 13, discussions of the energy flows in a hot box, Annex A2, the metering box wall loss flow, Annex A3, and flanking loss, Annex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT