Question

Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Varianc...

Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances

Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred fixed setup costs of $588,800 (salaries of 16 employees). The fixed costs provide a capacity of 36,800 hours (2,300 per employee at practical capacity). The setup activity was viewed as necessary, and the value-added standard was set at 2,300 hours. Actual setup hours used in the most recent period were 34,700.

Required:

1. Calculate the volume and unused capacity variances for the setup activity. Enter all amounts as positive values.

Volume Variance $
  • Favorable
  • Unfavorable
Unused Capacity Variance $
  • Favorable
  • Unfavorable

2. Prepare a report that presents value-added, non-value-added, and actual costs for setup.

Maquina Company
Value- and Non-Value-Added Cost Report
Value-Added Non-Value-Added Actual
Setting up $ $ $
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Part-1
Fixed Activity Rate (SP) =Fixed Setup Cost/ No. of Hour
$588800/36800=$16/Set upHour
Volume Variance= (SPXSQ-SPX AQ)
(16X2300)-(16X 36800)=$552000 UF
Unused Capacity Variance= (SPXAQ)-(SPX AU)
(16X36800)- (16X 34700)=33600F
Part-2: Value & Non-Value Added Cost Report
Value Added Non Value Added Actual
Setting Up (SPXSQ) Volume Variance SPX AQ
(16X 2300) (16X36800)
                      36,800                        5,52,000            5,88,800
Add a comment
Know the answer?
Add Answer to:
Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Varianc...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Varianc...

    Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...

  • Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company pro...

    Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...

  • Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made...

    Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...

  • Cost Report, Value Added and Non-Value Added Costs Sanford, Inc., has developed value-added standards for four...

    Cost Report, Value Added and Non-Value Added Costs Sanford, Inc., has developed value-added standards for four activities: purchasing parts, receiving parts, moving parts, and setting up equipment. The activities, the activity drivers, the standard and actual quantities, and the price standards for 20x1 are as follows: Activities Activity Driver Purchasing parts Receiving parts Purchase orders Receiving orders Number of moves Setup hours SQ AQ SP 3,100 4,570 $255 6,200 8,500 245 0 2,700 380 0 9,500395 Moving parts Setting up...

  • Value Added and Non-Value Added Costs, Unused Capacity For Situations 1 through 6, provide the following...

    Value Added and Non-Value Added Costs, Unused Capacity For Situations 1 through 6, provide the following information: a. An estimate of the non-value-added cost caused by each activity. If required, round your final answer to the nearest dollar. b. The root causes of the activity cost (such as plant layout, process design, and product design). C. The appropriate cost reduction measure: activity elimination, activity reduction, activity sharing, or activity selection, 1. It takes 48 minutes and five pounds of material...

  • Value Added and Non-Value Added Costs, Unused Capacity For Situations 1 through 6, provide the following...

    Value Added and Non-Value Added Costs, Unused Capacity For Situations 1 through 6, provide the following information: a. An estimate of the non-value-added cost caused by each activity. If required, round your final answer to the nearest dollar. b. The root causes of the activity cost (such as plant layout, process design, and product design). c. The appropriate cost reduction measure: activity elimination, activity reduction, activity sharing, or activity selection. Choose "Multiple" in the Root cause column, wherever there is...

  • Exercise 21-21 Overhead controllable and volume variances; overhead variance report LO P4 James Corp. applies overhead...

    Exercise 21-21 Overhead controllable and volume variances; overhead variance report LO P4 James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels 80% 10,000 25,000 Overhead Budget Production in units Standard direct labor hours Budgeted overhead Variable overhead costs Indirect materials Indirect labor Power Maintenance Total variable costs Fixed overhead costs...

  • Required 2 Required 1 Required 3 Compute the overhead volume variance. Classify as favorable or unfavorable....

    Required 2 Required 1 Required 3 Compute the overhead volume variance. Classify as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance. Do not round intermediate calculations.) Volume Variance Volume variance Required 1 Required 3 Required 1 Required 2 Required 3 Prepare an overhead variance report at the actual activity level of 9,000 units. Classify as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no...

  • James Corp. applies overhead on the basis of direct labor hours. For the month of May,...

    James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 25,000 Budgeted overhead Variable overhead costs Indirect materials $ 18,000 Indirect labor 25,000 Power 5,000 Maintenance 2,000 Total variable costs 50,000 Fixed overhead costs Rent of factory building 18,000 Depreciation—Machinery...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT