Question

can someone please provide steps for calculating IRR on a TI Nspire CX? I can calculate npv already, but I do not know how to use the irr function on ti nspire. the problem I am stuck on is number 10.

out-content-rid-14522766-1/courses/FINC3321-002-201 920/capital%20decisions%281 %29.pdf P9-10 Your company is considering two

thank you

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Calculation of NPV of projects
Year Discount Factor @ 12% Project C Project R
Cash flow Present Value Cash flow Present Value
0     1.00000 -$14,000.00 -$14,000.00 -$22,840.00 -$22,840.00
1     0.89286 $8,000.00 $7,142.86 $8,000.00 $7,142.86
2     0.79719 $6,000.00 $4,783.16 $8,000.00 $6,377.55
3     0.71178 $2,000.00 $1,423.56 $8,000.00 $5,694.24
4     0.63552 $3,000.00 $1,906.55 $8,000.00 $5,084.14
NPV $1,256.14 $1,458.79
Project NPV
C $1,256.14
R $1,458.79
Calculation of IRR of project
We can use the IRR excel formula to calculate the same.
At IRR , the NPV of project is equal to zero.
Project IRR
C 17.32%
R 15.00%
IRR method is most appropriate than NPV method when both the projects are equally risky.
Hence , I would suggest the project C should be purchased as it has higher IRR.
Add a comment
Know the answer?
Add Answer to:
Can someone please provide steps for calculating IRR on a TI Nspire CX? I can calculate npv alrea...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please use Excel to solve. NPV and IRR for Mutually Exclusive Projects 10. A company is...

    Please use Excel to solve. NPV and IRR for Mutually Exclusive Projects 10. A company is considering two mutually exclusive projects, A and B. Project A requires an initial investment of $200, followed by cash flows of $185, $40, and $15. Project B requires an initial investment of $200, followed by cash flows of S0, $50, and $230. What is the NPV and IRR for each of the projects? Which project should the company choose? The firm's cost of capital...

  • Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

    Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...

  • СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV...

    СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rat of return, and it is comparable to the - Select on a bond. The equation for calculating the IRR is: NPV = CF. + CF + СР + ... + =0 (1 + IRR) (1 + ru (1 + R) CF (1 + IRR) CFt is the expected...

  • 11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV...

    11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV A company is analyzing two mutually exclusive projects, s and L, with the following cash flows: 0 2 3 4 Project S$1,000T $906.76 $240 $5 $10 Project L$1,000 $0$250 $380 $792.79 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: 1 better project may or may not be the one with the higher IRR.) Round your answer to two...

  • NPV and IRR analysis of projects Thomas Company is considering two mutually exclusive projects. The firm,...

    NPV and IRR analysis of projects Thomas Company is considering two mutually exclusive projects. The firm, which has a cost of capital of 14%, has estimated its cash flows as shown in the following table: a. Calculate the NPV of each project, and assess its acceptability. b. Calculate the IRR for each project, and assess its acceptability. a. The NPV of project A is $ (Round to the nearest cent.) Х i Data Table (Click on the icon located on...

  • IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...

    IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: Project s $1,000 $886.43 $260 $5 $5 Project L $1,000 $10 $240 $400 $819.73 The company's WACC is 9.0% what is the IRR of the better project? Hint: The better project may or may not be the one th e hi her 1 R und your answer to tvo decimal places

  • When might the IRR rule provide different guidance regarding project selection than the NPV rule? a)...

    When might the IRR rule provide different guidance regarding project selection than the NPV rule? a) When a project has net expenditures (costs) that occur after positive cash inflows. b) When a project has two or more years of initial net expenditures, followed only by cash inflows. c) When a project has multiple IRRs. d) When deciding between mutually exclusive projects with different initial investment amounts. When might the IRR rule provide different guidance regarding project selection than the NPV...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • A, B, and C are the main ones I'm not sure about. NPV and IRR Analysis...

    A, B, and C are the main ones I'm not sure about. NPV and IRR Analysis Cummings Products is considering two mutually exclusive investments whose expected net cash flows are as follows: Expected Net Cash Flows Year Project A -$400 -528 -219 Project B -$650 210 210 -150 210 You A WN - 1,100 210 210 820 990 210 -325 210 a. Construct NPV profiles for Projects A and B. b. What is each project's IRR? c. If each project's...

  • This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows...

    This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT