What is the probability that the project will be completed within: (a) 21 days? (b) 22 days? (c) 25 days? Activity* a mb АВЗ AC св CD 3 3 3 CE BD 0 0 6 BE DF DE EF 4 4 10 Find: (a) the critic...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...