Question

An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....

An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000​, to reduce the annual probability of flooding to 0.364  during a period of 18 years before it would have to be deepened again. This procedure would also involve annual expenditures of $90,000 for minimal maintenance.

            One legislator in the area has proposed that a better solution would be to construct a​ flood-control dam at a cost of $8,000,000​, which would last​ indefinitely, with annual maintenance costs of not over $50,000.

She estimates that this project would reduce the annual probability of flooding to 0.205. In​ addition, this solution would provide a substantial amount of irrigation water that would produce annual revenue of ​$150,000

and recreational​ facilities, which she estimates would be worth at least $45,000 per year to the adjacent populace.

            If the​ state's capital is worth 11​%, perform​ B-C analysis and recommend the proposal to be adopted. Note that one of the two proposals must be​ adopted, as the​ do-nothing alternative will not be accepted by the​ legislature, no matter what the analysis shows. This means that only the incremental analysis between the two proposals need be done.

The​ B-C ratio for the​ "Improve channel" proposal is ______ ​(Round to 2 decimal places​)

The​ B-C ratio for the​ "Construct dam" proposal is ________ ​(Round to 2 decimal places​)

The incremental​ B-C ratio of​ "Construct dam" vs.​ "Improve channel" is _____ ​(Round to 2 decimal places​)

​Therefore, the recommended proposal is to

A.Improve the channel

B.Construct Dam

1 0
Add a comment Improve this question Transcribed image text
Answer #1

General Definition of BCR

A benefit-cost ratio (BCR) is an indicator showing the relationship between the relative costs and benefits of a proposed project, expressed in monetary or qualitative terms. If a project has a BCR greater than 1.0, the project is expected to deliver a positive net present value to a firm and its investors.

Calculation of Benefit - Cost Ratio or B-C Analysis

= Present Value of Projects Benefits/ Present Value of Project Cost

Discount rate = 11%

Yearly Loss on account of periodic Floods = 2,200,000*0.5 = $ 1,100,000

Option A - Improve the channel

Life of Channel = 18 Years

Annual Loss Reduction if channel is improved (Cash Inflow) = (0.5 - 0.364) * $1,100,000 = $149,600

Present Value of Annual Loss Reduction at 11% discount rate for 18 years

= 149,600 * Present Value Annuity Factor (11%, 18 Years) = 149,600 * 7.7016 = $1,152,162

Annual Maintenance Cost (Cash Outflow) = $90,000

Present Value of Annual Maintenance at 11% discount rate for 18 years

= 90,000 * Present Value Annuity Factor (11%, 18 Years) = 90,000 * 7.7016 = $693,144

Cost of Project (Cash Outflow) = $2,400,000

B-C Ratio = Benefits from Project/Cost of Project

= 1,152,162 / (693,144 + 2,400,000)

= 1,152,162 / 3,093,144 = 0.37

Option B - Construct Dam

Life of Dam = Indefinite (Perpetual)

Annual Loss Reduction if dam is constructed (Cash Inflow) = (0.5 - 0.205) * $1,100,000 = $324,500

Present Value of Annual Loss Reduction at 11% discount rate for perpetual period

= 324,500 / Discount Rate = 324,500 / 0.11 = $2,950,000

Annual Maintenance Cost (Cash Outflow) = $50,000

Present Value of Annual Maintenance at 11% discount rate for perpetual period

= 50,000 / Discount Rate = 50,000 / 0.11 = $454,545

Annual Revenue from water for Irrigation and Recreational Facilities (Cash Inflow) = (150,000 + 45,000) = $195,000

Present Value of Annual Additional Revenue at 11% discount rate for perpetual period

= 195,000 / Discount Rate = 195,000 / 0.11 = $1,772,727

Cost of Project (Cash Outflow) = $8,000,000

B-C Ratio = Benefits from Project/Cost of Project

= (2,950,000 + 1,772,727) / (8,000,000 + 454,545)

= 4,722,727 / 8,454,545 = 0.56

Decision = Under both the options, BCR is coming out to be less than one which implies that neither of the projects will deliver a positive Net Present Value to legislature.

However, since one of the options has to be adopted, Option B of Constructing the Dam is better compared to improving the channel since the BCR of option B is 0.56 which is greater than 0.37 of Option A of improving the channel.

Incremental BCR of the two projects

Increasing Order

Option B = Benefit = 4,722,727

Cost = 8,454,545

Option A = Benefit = 1,152,162

Cost = 3,093,144

Incremental BCR = Incremental Benefits / Incremental Costs

= (4,722,727 - 1,152,162) / (8,454,545 - 3,093,144)

= 3,570,565 / 5,361,401 = 0.67

For any clarification, please leave a comment.

Add a comment
Know the answer?
Add Answer to:
An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT