Given that the customer requirements for the process is (11.9, 12.1), using X bar and R chart, find Cp, Cpk and DPMO for the following samples (there are 16 samples). Assume the process is normally distributed.

Given that the customer requirements for the processis (11.9, 12.1), using X bar and R chart, find Cp, Cpk and DPMO for the f

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Compute X and R for each sample X is computed as average of the observations for each sample R is computed by subtracting the

For subgroup size, n = 5, value of control chart constant, d2 = 2.326 (from table of control chart constants)

Standard deviation = Rbar / d2 = 0.050/2.326 = 0.021

LSL = 11.9

USL = 12.1

mean (m) = Xdblbar = 12.000

Cp = (USL-LSL)/6s = (12.1-11.9)/(6*0.021) = 1.5873

Cpk = MIN((USL-m)/3s, (m-LSL)/3s)

= MIN((12.1-12.0)/(3*0.021), (12.0-11.9)/(3*0.021)) = 1.5873

For LSL, z value = (11.9-12.0)/0.021 = -4.76, F(z) = NORMDIST(-4.76) = 0.00000096

For USL, z value = (12.1-12.0)/0.021 = 4.76, F(z) = NORMDIST(4.76) = 0.99999904

Proportion defective = (1-0.99999904)+0.00000096 = 0.00000192

DPMO = 1.92 ~ 2

Add a comment
Know the answer?
Add Answer to:
Given that the customer requirements for the process is (11.9, 12.1), using X bar and R chart, find Cp, Cpk and DPMO for the following samples (there are 16 samples). Assume the process is normally di...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT