Answer: minimum no. of workers need to fulfill these needs are 9,
Rest of the answers are in table
Requirement |
7 |
4 |
4 |
4 |
7 |
5 |
5 |
total day off |
explanation |
||
Worker no. |
mon |
tue |
wed |
thu |
fri |
sat |
sun |
||||
1 |
2 |
provide off on tue and wed, because they have least requirement, 4+4=8 |
|||||||||
2 |
2 |
provide off on thu and wed, because they have least requirement 4+3=7 |
|||||||||
3 |
2 |
provide off on sat and sun, because they have least requirement, 3+3=6 |
|||||||||
4 |
2 |
provide off on tue and wed, because they have least requirement, 2+3=5 |
|||||||||
5 |
2 |
provide off on sat and sun, because they have least requirement, 2+2=4 |
|||||||||
6 |
2 |
provide off on thu and wed, because they have least requirement 2+0=2 |
|||||||||
7 |
2+1 |
provide off on thu and wed, because they have least requirement 2+0=2 |
|||||||||
8 |
6 |
only wed has requirement of 2 |
|||||||||
9 |
6 |
only wed has requirement of 1 |
8. A rates seven days a week. The daily worker requirements are estimated as follows: Day Requirements 7 Su Th 4. Each worker is required to work five days per week and each must have two consecu...
The daily requirements for highway patrol officers at Park City over the week are: Days M T W TH F S SU Requirement 11 9 6 7 5 3 2 Each officer works five days a week and must have two consecutive days off. How much total slack is generated from the schedule? A. greater than 11 days B. 11 days C. fewer than 9 days D. 10 days
PLEASE SHOW ALL WORK/INCLUDE FORMULAS NEEDED
Gerald Glynn manages the Michaels Distribution Center. After careful examination of his database information, he has determined the daily requirements for part-time loading dock personnel. The distribution center operates 7 days a week, and the daily part-time staffing requirements are Th Su Day Requirements Find the minimum number of workers Glynn must hire. Prepare a workforce schedule for these individuals so that each will have 2 consecutive days off per week and all staffing...
This is a cyclic scheduling problem unlike the other personnel
scheduling problems we considered earlier which were acyclic. In
this case, for example, a driver who starts his working week on
Friday will work for the rest of the week (F, Sa and Su) and the
first part of the following week (M and Tu) while is taking off W
and Th (see attached file). In other words, his schedule spans not
just one week (cycle) but two. The decision...
Problem 4-09 (Algorithmic) Epsilon Airlines services predominately the eastern and southeastern United States. The vast majority of Epsilon's customers make reservations through Epsilon's website, but a small percentage of customers make reservations via phone. Epsilon employs call-center personnel to handle these reservations along with any problems with the website reservation system and for the rebooking challenge for Epsilon's magement team. Having too many employees on hand of flights for customers if their plans change or their travel s disrupted. Staffing...
Hi,
I am requesting your help. Some of those that I am not sure if I
am right?
Thank you,
Michelle
________________________________
You work at Ford Motor Company and are responsible for determining weekly production capacity for the Juarez, Mexico assembly plant. There are 21 days left in the production month. Your sales manager just informed you that 4,725 vehicles need to be produced in the upcoming days to meet projected sales demand in the United States 21. Your production...
I have this case study to solve. i want to ask which
type of case study in this like problem, evaluation or decision? if
its decision then what are the criterias and all?
Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...