2. [10] A segment of interstate highway requires the construction of an embankment of 500,000 yds. The embankment fills to be compacted to a minimum of 90% of Modified Proctor maximum dry den...
3. Modified Proctor compaction test results for a soil at a construction site indicated that the maximum dry density ya = 125 lb/ft at an optimum water content Wopt = 9.5%. Assuming specific gravity of the mineral solids G=2.65, calculate: (a) the void ratio at the maximum dry density (b) the degree of saturation Sat maximum dry density.
Soil Mechanics Problem 2 (26 points) Results from a standard Proctor compaction test yield an Optimum Moisture Content (OMC) of 12% and a maximum dry unit weight of 18.1 kN/m. Given this information, address the following questions. a) The soil was used to construct an embankment on a construction site. A sand cone test indicated that a layer of the compacted fill had a total unit weight of 19.8 kN/m3 and a moisture content of 11%. Specifications call for the...