Question

There is an 84 percent chance that the construction of a building will be completed by the required date; on the other hand, there is a 20 per cent chance that ABC, a sub-contractor of the project, is...

There is an 84 percent chance that the construction of a building will be completed by the required date; on the other hand, there is a 20 per cent chance that ABC, a sub-contractor of the project, is not respecting the delivery date of its contract. However, the odds of completing the building on the required date, as long as the ABC respects its delivery date, are 90 out of 100.


a) What is the probability that the building will be completed on the required date if the ABC subcontractor does not respect its delivery date?
b) What is the probability that ABC will respect its delivery date given that the construction of the building will be completed by the required date?

Answer should be: a) 0.6 b) 0.8571

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Constauchion ra Now, oc rifg) : PO-P (COR) (034)-(0.72) _ (o .20 0.2 P(c) C) (o 3) (0.8) o·89

Add a comment
Know the answer?
Add Answer to:
There is an 84 percent chance that the construction of a building will be completed by the required date; on the other hand, there is a 20 per cent chance that ABC, a sub-contractor of the project, is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management...

    TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management (SCM) group at Torento Construction Inc. (NCG), was in his office in Torento, Ontario, trying to organize the thoughts running through his head as a result of a recent bidding to save operating costs at NCG. There was no problem in terms of the final outcome; in fact, the bid was going to result in cost savings of 25 per cent, which was exactly...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT