Question

When the unexpected occurs.... Oh no! There has been a major unexpected disruption in your project plans! The Manchest...

When the unexpected occurs....
Oh no! There has been a major unexpected disruption in your project plans!
The Manchester United Soccer Club Committee is extremely concerned with the timelines. The
tournament is set to commence in six (6) weeks yet the schedule has fallen behind and in danger
of not meeting the target date! If the project is not fast tracked as an urgent priority there is a real
danger of the tournament not taking place. This will result in significant reservation bookings,
expenses and funds lost. The reputation of Manchester United will end up in tatters and the club’s
financial position will take a significant hit!
This is the email you have received from your Investor:
February 16, 2019
Arthur Pitsas
Chairman
Manchester United Soccer Club Committee
To the Project Management Team,
I am writing to bring to your attention the current issues with the Manchester United Tournament.
The committee is extremely concerned with the timelines. With only 6 weeks to go before
tournament kick-off, we are finding that the schedule has slipped. Grounds haven’t yet been
reserved, accommodation not yet finalised and sponsorship is lagging expectations. We do not
have a full quota of volunteers either!
The project team is required to front the Committee to provide:
 Project status update
 Honest appraisal of the schedule
 Fast tracking options
 Additional resource requirements
 Outstanding matters to be addressed
 What needs to be done to have the project back on track
We are in serious risk of losing the funds injected into the tournament and major reputational
losses.
The committee requires this project back on track quickly

Question: identify risks relating to the news,Demonstrate an excellent use of risk assessment measures or tools to assess the consequences of the identified risks and provide excellent details and justifications of risk management strategy.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Some of the risks that are related to the news are

  1. The activities are moving behind the schedule and there is a major risk that the entire tournament might not take place.
  2. Facilities might not be arranged at the start date of the tournament.
  3. Grounds might not get reserved for the tournament to take place. The ground authorities might give the ground to other bookings, when the grounds are not booked on those particular dates of the tournaments.
  4. If the tournament does not take place the reservation costs must be refunded.
  5. Sponsorships are not finalized and if the sponsorship is not coming for the players requirements, then the team management would face a lot of financial loss.
  6. Accommodation for the players and the support staffs are not identified. Last minute arrangements would definitely see a hike in the price of the bookings.
  7. Volunteers are not identified to carry out the jobs that are pending on a full scale basis.

Above mentioned are the risks that are identified.

Some of the major consequences of the risks that are identified are

  1. The would a huge loss for the company financially if all these items are arranged at the last minute.
  2. If the tournament do not take place, there would be loss of reputation. It would affect the future business of the company.
  3. The employee morale in the company would be very low, as they were not able to deliver as per the requirements.

All these risks could be mitigated and to a great extent avoided, by putting in place a risk management strategy.

  1. First a management plan must be devised as to what is to be done first according to the priority and the requirements of the tournament.
  2. The project leader must accept the risk management strategy, and must deploy the adequate resources to the various parts of the plan to be executed effectively.
  3. Resources must be allocated to see the accommodation bookings, sponsor confirmations, travel bookings, grounds availability.
  4. A monitoring team must be set up to see whether the allocated resources to the various requirements are functioning effectively to complete the tasks within the timelines.

Thus with this strategy, the tournament could take place according to the set target dates.

Add a comment
Know the answer?
Add Answer to:
When the unexpected occurs.... Oh no! There has been a major unexpected disruption in your project plans! The Manchest...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager,...

    Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...

  • Term Project You will both write and orally present your project. Your write-up of the project...

    Term Project You will both write and orally present your project. Your write-up of the project is due at the beginning of the class meeting on Monday, November 4, 2019. The teacher expects (but does not guarantee) that students will then present their projects sometime during the remaining class periods, but we will not yet have completed the chapter presentations, so the exact schedule will be worked out later. You may use any format which is sensible to the intended...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • HDT Truck Company HDT Truck Company has been located in Crown Point, Indiana, since 1910. Its...

    HDT Truck Company HDT Truck Company has been located in Crown Point, Indiana, since 1910. Its only products— large trucks—are built to individual customer specifications. The firm once produced automobiles but dropped out of the auto business in 1924. The firm nearly went out of business in the late 1930s, but by 1940 its fortunes were buoyed by receipt of several military contracts for tank retrievers—large-wheeled vehicles that can pull a disabled tank onto a low trailer and haul it...

  • What should have Merck & Co, Inc done differently in regards to river blindness? Merck &...

    What should have Merck & Co, Inc done differently in regards to river blindness? Merck & Company, Inc.: Having the Vision to Succeed by Stephanie Weiss and David Bollier An Expensive Care for a Poor Market In 1978, Dr. P. Roy Vagelos, then head of the Merck research labs, received a provocative memorandum from a senior researcher in parasitology, Dr. William C. Campbell. Dr. Campbell had made an intriguing observation while working with ivennectin, a new antiparasitic compound under investigation...

  • Case 2: Going to The X-Stream Gil Reihana is the chief executive officer of X-Stream, an...

    Case 2: Going to The X-Stream Gil Reihana is the chief executive officer of X-Stream, an Auckland-based company that assembles personal computers for the New Zealand and Australian markets, and sells them through a number of chain stores and independent retailers. He started the company six years ago, at the age of 25, after graduating from university with a Bachelor’s degree in Information Technology and Management. To establish the company, Reihana invested $300 000 he had inherited and persuaded various...

  • What should Ajanta do about its recent order from SF? AJANTA PACKAGING: KEY ACCOUNT MANAGEMENT Sandeep Puri and Rakesh Singh wrote this case solely to provide material for class discussion...

    What should Ajanta do about its recent order from SF? AJANTA PACKAGING: KEY ACCOUNT MANAGEMENT Sandeep Puri and Rakesh Singh wrote this case solely to provide material for class discussion. The authors do not intend to iustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality This publication may not be transmitted, photocopied, digitized, or otherwise reproduced in any form or by any means without the...

  • Please read the article and answer about questions. You and the Law Business and law are...

    Please read the article and answer about questions. You and the Law Business and law are inseparable. For B-Money, the two predictably merged when he was negotiat- ing a deal for his tracks. At other times, the merger is unpredictable, like when your business faces an unexpected auto accident, product recall, or government regulation change. In either type of situation, when business owners know the law, they can better protect themselves and sometimes even avoid the problems completely. This chapter...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.