During 2020, Sunland Company started a construction job with a
contract price of $1,408,000. The job was completed in 2022. The
following information is available. The contract is
non-cancellable.
2020 | 2021 | 2022 | ||||
---|---|---|---|---|---|---|
Costs incurred to date |
$352,000 | $726,000 | $941,600 | |||
Estimated costs to complete |
528,000 | 242,000 | 0 | |||
Billings to date (non-refundable) |
264,000 | 792,000 | 1,408,000 | |||
Collections to date |
237,600 | 712,800 | 1,254,000 |
QUESTION:
A) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
B) Prepare all necessary journal entries for 2021. (Use Materials, Cash, Payables for costs incurred to date.)
Solution A:
Computation of % of completion, revenue recognition and Gross Profit - Sunland company | ||||||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | % of completion (D) (B/C) |
Contract Price (E) |
Total Revenue to be recoganized (F) (E * D) | Revenue for current period (G) | Gross Profit (H) (G - A) |
2020 | $352,000 | $352,000 | $880,000 | 40.00% | $1,408,000 | $563,200 | $563,200 | $211,200 |
2021 | $374,000 | $726,000 | $968,000 | 75.00% | $1,408,000 | $1,056,000 | $492,800 | $118,800 |
2022 | $215,600 | $941,600 | $941,600 | 100.00% | $1,408,000 | $1,408,000 | $352,000 | $136,400 |
Solution B:
Journal Entries - Sunland Company - 2021 | |||
Event | Particulars | Debit | Credit |
1 | Construction in Progress Dr | $374,000.00 | |
To Matreial, cash, payables | $374,000.00 | ||
(To record construction cost incurred) | |||
2 | Accounts receivables Dr | $528,000.00 | |
To Billings on construction contract | $528,000.00 | ||
(To record progress billings) | |||
3 | Cash Dr | $475,200.00 | |
To Accounts receivables | $475,200.00 | ||
(To record collection from customer) | |||
4 | Construction in Progress Dr | $118,800.00 | |
Cost of construction Dr | $374,000.00 | ||
To Revenue from long term contracts | $492,800.00 | ||
(To record revenue and gross profit) |
During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 20...
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $820,500 $1,077,000 Estimated costs to complete 585,800 273,500 –0– Billings to date 297,000 894,000 1,580,000 Collections to date 273,000 816,000 1,419,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...
During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $902,000 $1,070,000 Estimated costs to complete 636,300 198,000 –0– Billings to date 303,000 899,000 1,620,000 Collections to date 273,000 807,000 1,412,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amountenter...
During 2020, Stellar Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $749,360 $1,070,000 Estimated costs to complete 636,300 352,640 –0– Billings to date 302,000 907,000 1,620,000 Collections to date 268,000 815,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...