Question

5. During Year 1, Gates Corp. started a construction job with a total contract price of $4,000,000. The job was completed on
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1

  1. To record the cost incurred:

Work-in-progress

$990,000

Accounts payable and others

$990,000

  1. To record the amount billed:

Accounts receivable

$1600,000

Billings

$1600,000

  1. To record the collections:

Cash

$1200,000

Account receivable

$1200,000

Answer 2

Gross profit for 1st year= Billed to customer- Actual cost incurred

                                             =$1600000-$990000

                                          = $610,000

Add a comment
Know the answer?
Add Answer to:
5. During Year 1, Gates Corp. started a construction job with a total contract price of $4,000,000. The job was com...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job...

    During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was complete...

    During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job...

    During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $902,000 $1,070,000 Estimated costs to complete 636,300 198,000 –0– Billings to date 303,000 899,000 1,620,000 Collections to date 273,000 807,000 1,412,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amountenter...

  • During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job...

    During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $820,500 $1,077,000 Estimated costs to complete 585,800 273,500 –0– Billings to date 297,000 894,000 1,580,000 Collections to date 273,000 816,000 1,419,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...

  • During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...

  • Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000....

    Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...

  • During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...

  • During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT