Question

3. Consider Table 2 Table 2 Year 3 Year 4 Cash flow Year 2 Year 0 Year 1 Cash flovw Cash flow Cash flow 70 Cash flow Project

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a)

NPV of a project = Present value of cash inflow – Initial investment cost

Calculation of present value of cash inflow where cost of capital is given 15%

$80 ˣPV(15%,1y) + $70 ˣPV(15%,2y) + $70 ˣPV(15%,3y) + $30 ˣPV(15%,4y)

= $80 ˣ .870 + $70 ˣ.756 + $70 ˣ.658 + $30 ˣ.572

= $69.6 + $52.92 + $46.06 + $17.16

=$185.74

Initial investment cost = $150 which is made entirely through equity

NPV of a project = Present value of cash inflow – Initial investment cost

                   NPV = $185.74 - $150

                            = $35.74

Answer b)

Determination of cost of equity when investment ratio between equity and debt is 1:1

If we consider determination of cost of equity before taxes

As per MM theorem the formula of cost of equity is

Cost of equity = Cost of unlevered equity + Debt / Equity (cost of Unlevered equity – cost of debt)

= 15% + .75/.75 (15% - 10%)

= 15% - 5%

= 10%

Therefore, cost of equity = 10% when debt capital is introduced at 1:1 ratio

Calculation of WACC

Calculation of weighted average cost of capital

WACC

Year

Item

Amount

Weight

Pre tax cost

Tax sheild

Post tax cost

Weighted cost(WACC)

Percentage(%)

1

Equity

75

0.5

7.5

N.A.

7.5

3.75

Debt

75

0.5

7.5

3

4.5

2.25

Total cost

6

4

Year 2

Equity

75

0.5

7.5

7.5

3.75

Debt

75

0.5

7.5

2

5.5

2.75

Total cost

6.5

4.33

Year 3

Equity

75

0.5

7.5

7.5

3.75

Debt

75

0.5

7.5

0.75

6.75

3.375

Total cost

7.125

4.75

Year 4

Equity

75

0.5

7.5

7.5

3.75

Debt

75

0.5

7.5

0.24

7.26

3.63

Total Cost

7.38

4.92

Answer 3

Calculation of net present value of the project by using WACC rate

NPV = $80 ˣPV(4%,1y) + $70 ˣPV(4.33%,2y) + $70 ˣPV(4.75%,3y) + $30 ˣPV(4.92%,4y) – Initial capital

=    14+13.13 +12.18+5.06 - $150

=$44.37 - $150

NPV = ($105.63)

Answer d)

Solely financed by equity capital + present value of financing

= $75 + $80 ˣPV(10%,1y) + $70 ˣPV(10%,2y) + $70 ˣPV(10%,3y) + $30 ˣPV(10%,4y)

= Total value of this summation is APV

Add a comment
Know the answer?
Add Answer to:
3. Consider Table 2 Table 2 Year 3 Year 4 Cash flow Year 2 Year 0 Year 1 Cash flovw Cash flow Cash flow 70 Cash flow Pr...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 6...

    NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 60 110 110 (200) (200) (200) 75 40 60 75 40 60 110 0.80 0.24 2.00 3.60 Interest Tax Shield Additional information for all projects 15% Cost (required return) on unlevered equity (%) Cost of debt capital (%) Corporation tax rate (%) Financing of each project: Debt 10% 20% 100 100 Equit alculate the value of project...

  • 2. Consider Table 1 Table 1 Levered Firm L Liabilities and Shareholders' Equit Assets 100 200 Equi Assets 100 Debt...

    2. Consider Table 1 Table 1 Levered Firm L Liabilities and Shareholders' Equit Assets 100 200 Equi Assets 100 Debt Total 200 200 Total Additional Financial Information for Levered Firm L 80 Earnings Before Interest and Tax Cost of debt capital 8% 12% 255% Cost of unlevered equi Corporate tax rate 15% 30% Personal tax rate on debt income Personal tax rate on equity income Consider Table 1. Calculate the interest expense, earnings before taxes, the tax liability, and the...

  • You are considering a project with an initial investment of $20 million and annual cash flow...

    You are considering a project with an initial investment of $20 million and annual cash flow (before interest and taxes) of $5,000,000. The project’s cash flow is expected to continue forever. The tax rate is 34%, the firm’s unlevered cost of equity is 18% and its after-tax cost of debt is 6.60%. The only side-effect from the use of debt that you are concerned about is related to the tax shield. If the project were to be financed with 100%...

  • Consider an all-equity project with the following characteristics: ·         Cash inflows = $18,000 per year in...

    Consider an all-equity project with the following characteristics: ·         Cash inflows = $18,000 per year in perpetuity ·         Cash outflows (costs) =50% of cash inflows ·         Corporate tax rate = 35% ·         Cost of capital of all-equity project = 12% Now suppose that the management issues debt to finance a share repurchase program. The new cost of capital of the levered project is 10%. (Hint: Solve part a. first). a) Using this information, determine the present value of the tax...

  • Your firm’s market value balance sheet is given as follows: Market Value Balance Sheet Excess cash...

    Your firm’s market value balance sheet is given as follows: Market Value Balance Sheet Excess cash $30M Debt $230M Operating Assets $500M Equity $300M Asset Value $530M Debt + Equity $530M Assume that the you plan to keep the firm’s debt-to-equity ratio fixed. The firm’s corporate tax rate is 50%. The firm’s cost of debt is 10% and cost of equity is 20%. Now, suppose that you are considering a new project that will last for one year. According to...

  • Arbitra Inc.'s current capital structure is 30% debt and 70% equity. The expected return on its...

    Arbitra Inc.'s current capital structure is 30% debt and 70% equity. The expected return on its debt is 5%, its equity Beta is 1.1. The riskfree rate is 2%, and the expected return on the market is 10%. Consider now the following additional information. The government of Bigland, where Arbitra Inc. is located, introduces a 40% corporate income tax rate. Arbitra Inc. (capital structure still 50% debt and 50% equity) has only one project which is expected to generate $1000...

  • Company J is considering a project with a 4-year lifespan. The initial cash flow estimate is...

    Company J is considering a project with a 4-year lifespan. The initial cash flow estimate is $125million in the first year increasing by $125million in each of the years 2 through 4. To begin the project, the company will need to invest $1billion dollars. Company J would like to cover the initial investment amount with existing internal resources and thereby not borrow. As such it remains an all-equity firm. The unlevered cost of its equity is 10%, similar to other...

  • Consider a project with free cash flow in one year of $130,000 in a weak market...

    Consider a project with free cash flow in one year of $130,000 in a weak market or $180,000 in a strong market, with each outcome being equally likely. The initial investment required for the project is $100,000, and the project's unlevered cost of capital is 20%. The risk-free interest rate is 10%. (Assume no taxes or distress costs.) a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...

  • Consider a project with free cash flow in one year of $130,000 in a weak market...

    Consider a project with free cash flow in one year of $130,000 in a weak market or $180,000 in a strong market, with each outcome being equally likely. The initial investment required for the project is $100,000, and the project's unlevered cost of capital is 20%. The risk-free interest rate is 10%. (Assume no taxes or distress costs. a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...

  • WorI 2. Consider Table 1 Table l Corporate tax Personal tax ratePersonal tax rate Cost of Firm AssetsDebt Equity unleve...

    WorI 2. Consider Table 1 Table l Corporate tax Personal tax ratePersonal tax rate Cost of Firm AssetsDebt Equity unlevered equity | on equity (%) rate (%) on debt (%) 15% 100 0 100 0% 0% 0% 15% 100 50 50 20% 0% 0% 100 100 50 50 15% 20% 20% 10% 50 15% 20% 10% 50 4 20% Earnings Before Interest and Taxation (EBIT) is 50 for all firms Cost of debt capital is 10% for all firms (a)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT