Trend Reporting for Non-Value Added Costs Cicleta Manufacturing has four activities: receiving materials, assembly, exp...
AQ Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities, expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 20xl (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver SO SP Receiving Receiving orders 5,600 28,500 $9 Assembly Labor hours 117,000 142,500 7 Expediting Orders expedited 0 9,500 22 Storing...
Value- and Non-Value-Added Cost Reporting Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 20x1 (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver SQ AQ SP Receiving Receiving orders 12,000 18,000 $21 Assembly Labor hours 75,000 90,000 15 Expediting Orders...
Value- and Non-Value Added Cost Reporting Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 2014 (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver SQ AQ SP Receiving Receiving orders 13,600 28,500 $24 Assembly Labor hours 117,000 142,500 1 7...
Cornerstone Exercise 12.1 (Algorithmic) Value- and Non-Value-Added Cost Reporting Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 2014 (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver SQ AQ SP Receiving Receiving orders 7,200 19,500 $12 Assembly Labor hours 81,000 ...
Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary, The following data pertain to the four activities for the year ending 2014 (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver SQ AQ SP Receiving Receiving orders 15,200 22,500 Labor hours 93,000 112.500 19 Assembly Expediting Storing Orders expedited 0 7,500 64 Number...
Cost Report, Value Added and Non-Value Added Costs Sanford, Inc., has developed value-added standards for four activities: purchasing parts, receiving parts, moving parts, and setting up equipment. The activities, the activity drivers, the standard and actual quantities, and the price standards for 20x1 are as follows: Activities Activity Driver Purchasing parts Receiving parts Purchase orders Receiving orders Number of moves Setup hours SQ AQ SP 3,100 4,570 $255 6,200 8,500 245 0 2,700 380 0 9,500395 Moving parts Setting up...