Date Accounts Debit Credit
01.06.20X1 Cash $450,000
To Sale of Equipment $428,000
To Maintenance Contract ( 450000-428000) $22,000
( Sale of equipment with 3 Year warranty)
30-11-20X1 sale of Equipment $428,000
P&L $428,000
( Revenue Booked)
30-11-20X1 Maintenance Contract Amount charge $22,000
Discount on Maintenance Contract $67,900
Provision for Maintenance for 3 year $89,900
( Provision for 3 Year Maintenance contract created and Discount booked according market rate)
P&L A/c Dr. $67,900
To Discount on Maintenance contract $67,900
( Discount booked in PL A/c)
Add a comment
Know the answer?
Add Answer to:
o Arrow Co. entered into a contract with a customer for $450,000. The contract is for the delivery of equipment and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4 SorCo. Inc. has just entered into a sale agreement with a customer. The contract is...

    4 SorCo. Inc. has just entered into a sale agreement with a customer. The contract is for $1,150,000. However, the payments will be made as follows: 1 August 20X1 on date of delivery $510,000, 1 August 20X2 $320,000 and 1 August 20x3 $320,000. SorCo has estimated that the Interest rate required for this customer is 7% ints Required: Prepare the Jounal entry required to record the sale on 1 August 20X1 and the recelpt of cash on 1 August 20X2...

  • On November 1, 2018, Green Valley Farm entered into a contract to buy a $150,000 harvester...

    On November 1, 2018, Green Valley Farm entered into a contract to buy a $150,000 harvester from John Deere. The contract required Green Valley Farm to pay $150,000 in advance on November 1, 2018. The harvester (cost of $110,000) was delivered on November 30, 2018. The journal entry to record the delivery of the equipment includes a

  • Check my wor On January 1, 2021, Splash City issues $450,000 of 7% bonds, due in...

    Check my wor On January 1, 2021, Splash City issues $450,000 of 7% bonds, due in 10 years, with interest payable semiannually on June 30 and December 31 each year. The market interest rate on the issue date is 8% and the bonds issued at $419,422. 2. If the market interest rate drops to 7% on December 31, 2022, it will cost $450,000 to retire the bonds. Record the retirement of the bonds on December 31, 2022. (If no entry...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On January 1, 2021, Splash City issues $450,000 of 7% bonds, due in 10 years, with...

    On January 1, 2021, Splash City issues $450,000 of 7% bonds, due in 10 years, with interest payable semiannually on June 30 and December 31 each year. Assuming the market interest rate on the issue date is 8%, the bonds will issue at $419,423. Required: 1. Complete the first three rows of an amortization table. (Round your intermediate and final answers to the nearest whole dollar.) Date Cash Paid Interest Expense Change in Carrying Value Carrying Value 1/1/21 6/30/21 12/31/21...

  • On 1/1/X1, Gerri Corp. borrowed $450,000 by agreeing to a 9%, 9-year installment note with the...

    On 1/1/X1, Gerri Corp. borrowed $450,000 by agreeing to a 9%, 9-year installment note with the bank. The note's proceeds will eventually be used to purchase a building. The journal entry to record the note is already shown in the journal below The note will be paid back in nine equal annual installment payments of $ 75,059 on December 31 of each year beginning December 31, 20X1 Required: Using the above information, prepare the journal entries to record the first...

  • On January 1, Snipes Construction paid for earth-moving equipment by issuing a $450,000, 4-year note that...

    On January 1, Snipes Construction paid for earth-moving equipment by issuing a $450,000, 4-year note that specified 2% interest to be paid on December 31 of each year. The equipment’s retail cash price was unknown, but it was determined that a reasonable interest rate was 5%. (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.) At what amount should Snipes record the equipment...

  • On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...

    On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $36.800 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $18.400 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $18.400 to Green. Revis estimates an 80% chance that cost savings will reach the...

  • Sarjit Systems sold software to a customer for $177,000. As part of the contract, Sarjit promises...

    Sarjit Systems sold software to a customer for $177,000. As part of the contract, Sarjit promises to provide "free" technical support over the next six months. Sarjit sells the same software without technical support for $154,000 and a stand-alone six-month technical support contract for $66,000, so these products would sell for $220,000 if sold separately. Prepare Sarjit's journal entry to record the sale of the software. (If no entry is required for a transaction/event, select "No journal entry required" in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT