Question

Question on resource leveling 1. Use the following data in order to make a manpower loading chart, a cash-flow chart, and a progress S (banana curve) of practice problem #3 (show a loaded bar chart, with float, and a histogram for both costs and men). The banana curve should show both early start/finish and late start/finish costs. The cash and manpower charts are to show early start and finish information. It is not necessary to produce the late start/finish charts. The owner cannot pay more than $550/ day and the owner only have 14 workers. Level the resource and cost loaded bars accordingly. (only early and late start). This assignment is not to be done with CPM software do it by hand or with excel. One point will be deducted per error Activity Duration #of men/day total cost S100 cost/day 810 1096 990 550 1100 1758 90
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Question on resource leveling 1. Use the following data in order to make a manpower loading chart, a cash-flow char...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT