12. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table....

12. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are:

Year Cash Flow

Year 1 $375,000

Year 2 400,000

Year 3 300,000

Year 4 475,000

If the project’s desired rate of return is 8.00%, the project’s NPV—rounded to the nearest whole dollar—is . ($281,958/ $299,580/ $317,202/ $352,447)

Which of the following statements indicates a disadvantage of using the regular, or conventional, payback period for capital budgeting decisions? Check all that apply.

The payback period is calculated using net income instead of cash flows.

The payback period does not take into account the time value of money effects of a project’s cash flows.

The payback period does not take into account the cash flows produced over a project’s entire life.

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1.Initial cash flow= $375,000 + $400,000 + $300,000/2

= $375,000 + $400,000 + 150,000

   =925,000.

Net present value is calculated using a financial calculator by inputting the below:

  • •   Press the CF button.
  • •   CF0= -$925,000. It is entered with a negative sign since it is a cash outflow.
  • •   Cash flow for each year should be entered.
  • •   Press Enter and down arrow after inputting each cash flow.
  • •   After entering the last cash flow cash flow, press the NPV button and enter the desired rate of return is 8%.
  • •   Press enter after that. Press the down arrow and CPT buttons to get the net present value.

The net present value of cash flows of the project is $352,446.60 \rightarrow$352,447.

2.   A disadvantage of the regular payback period is that it does not take the time value of money effects of a project’s cash flow into account.

In case of any query, kindly comment on the solution

Add a comment
Know the answer?
Add Answer to:
12. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • 12. The NPV and payback period Suppose you are evaluating a project with the cash inflows...

    12. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 Year 2 Year 3 $325,000 400,000 300,000 Year 4 325,000 If the project's desired...

  • Calculate NPV based on cash flow and payback period

    Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years.The project's annual cash flows are:YearCash FlowYear 1$375,000Year 2450,000Year 3300,000Year 4400,000If the project’s desired rate of return is 9.00%, the project’s NPV—rounded to the nearest whole dollar—is     .Which of the following...

  • Suppose you are evaluating a project with the cash inflows shown in the following table. Your...

    Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $300,000 Year 2 400,000 Year 3 Year 4 400,000 475,000 If the project's desired rate of return is 7.00%, the...

  • Suppose you are evaluating a project with the expected future cash inflows shown in the following...

    Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $475,000 Year 3 $400,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 10%, the project’s NPV...

  • Suppose you are evaluating a project with the expected future cash inflows shown in the following...

    Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $425,000 Year 3 $475,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 10%, the project’s NPV...

  • The NPV and payback period What information does the payback period provide? Suppose you are evaluating...

    The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $325,000 Year 2 $450,000 Year 3 $450,000 Year 4 $475,000 If the...

  • Suppose you are evaluating a project with the expected future cash inflows shown in the following...

    Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Year 1 Year 2 Year 3 Year 4 Cash Flow $375,000 $425,000 $450,000 $475,000 If the project's weighted average cost of capital (WACC) is 7%, the project's NPV...

  • 5. The NPV and payback period What information does the payback period provide? Suppose you are...

    5. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $350,000 Year 2 $475,000 Year 3 $400,000 Year 4 $475,000 If...

  • 7. The NPV and payback period What information does the payback period provide? Suppose you are...

    7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $375,000 Year 2 Year 3 Year 4 $475,000 $475,000 $475,000 If...

  • Suppose you are evaluating a project with the expected future cash inflows shown in the following...

    Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. If the project's ~WACC~ is 7%, the project's NPV (rounded to the nearest dollar) is: Year Cash Flo Year 1 $300,000 Year 2 $450,000 Year 3 $450,000 Year 4...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT