What minimum uniform period cash flow for a project in periods 2 through 9 is required to make the discounted payback period be period 9 using an interest rate of 8.0 % if the year zero cash flow is -90,000 and the year one cash flow is -25,000?
Equating the present value of all cash flows to zero:
i = 8%
minimum uniform period cash flow = A
0 = -90000 -25000/1.08 + A/1.082 + A/1.083 + .... + A/1.089
A/1.082 + A/1.083 + .... + A/1.089 = 113148.1
A = 21264.6
What minimum uniform period cash flow for a project in periods 2 through 9 is required to make the discounted payback pe...
What minimum uniform period cash flow for a project in periods 2 through 9 is required to make the discounted payback period be period 9 using an interest rate of 8.0 % if the year zero cash flow is -90,000 and the year one cash flow is -25,000?
Discounted payback period) Assuming an appropriate discount rate of 11 percent, what is the discounted payback period on a project with an initial outlay of $100,000 and the following cash flows? Year 1 $30,000 Year 2 $35,000 Year 3 $25,000 Year 4 $25,000 Year 5 $30,000 Year 6 $20,000 The project's discounted payback period is years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(240) 72 80 95 If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Discounted payback period) The Callaway Cattle Company is considering the construction of a new feed handling system for its feed lot in Abilene, Kansas. The new system will...
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 - $180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 -$180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____ ?
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)
What is the DISCOUNTED PAYBACK PERIOD for the following project? Discount Rate 6.00% Investment $15,000.00 Cash Flow Year 1 $3,000.00 Cash Flow Year 2 $4,000.00 Cash Flow Year 3 $5,000.00 Cash Flow Year 4 $6,000.00
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) 85 60 95 If the project's appropriate discount rate is 12 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)