Develop a materials requirement plan (MRP) for component parts X and F over the next eight weeks. Data on all lead times, current inventory and ordering rules are given below: Scheduled receipts are: Period 1: 20 B’s, 18 W’s; Period 2: 20 S’s, 15 F’s. A sample MRP table is provide below.
ITEM |
LEADTIME (WKS) |
ON HAND |
LOT-SIZING RULE |
B |
2 |
5 |
Lot-for-lot |
S |
2 |
2 |
Lot-for-lot |
X |
1 |
5 |
Multiples of 25 |
W |
1 |
2 |
Multiples of 12 |
F |
1 |
10 |
Multiples of 30 |
K |
1 |
3 |
Lot-for-lot |
Q |
1 |
15 |
Multiples of 30 |
M |
1 |
0 |
Lot-for-lot |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
Gross requirements |
||||||||
Schedule receipts |
||||||||
Projected on hand |
||||||||
Net requirements |
||||||||
Planned order receipt |
||||||||
Planned order release |
Note please show up the calculations
The Bloomington Bike Company produces two models: the Basic and the Supra. Herb Hoosier, the owner, p...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
A company manufactures two types of DVD players, A and B. Although there are differences among the products, there are a number of common parts within each player. Each model A requires one subassembly C and two subassembly D’s. Each subassembly C requires two F’s and two G’s. Each subassembly D requires two units of F. Each F requires two units of raw material I, while each G requires one unit of raw material H. Each model B requires two...
i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...