The answer is
The NPVs of the two projects are equal
Crossover rate is the rate at which NPV of two projects intersect i.e. they are equal
IRR is the rate at which NPV = 0
Question 6 1 When comparing two projects using a NPV profile, the crossover-rate is the rate at which the NPVs of t...
1. Calculate the net present
value (NPV) for both projects, and determine which project should
be accepted based on NPV. Round both NPVs to the nearest
dollar.
2. Calculate the internal rate of return (IRR) for both
projects, and determine which project should be accepted based on
IRR.
3. Calculate the net present value (NPV) for both projects using
the crossover rate as your discount rate. Round both NPVs to the
nearest dollar.
Please show all work. Thank you.
Use...
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions): 2 $20 $8 Project A -$21 $14 $9 $3 Project B -$35 a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $...
Problem 11-6 NPV Your division is considering two projects with the following cash flows (in millions): - T Project A $14 $20 Project B -$15 $5 a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $ million Project...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is...
s NPV Your division is considering two projects with the following cash flows (in millions): o 1 2 3 + Project -$35 $4 $14 $20 A Project -$15 $a $5 $1 B a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus...
NPV Your division is considering two projects with the following cash flows (in millions): 1 3 $8 $8 $3 Project A -$17 -$26 $9 Project B $13 $10 a. What are the projects' NPVS assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $ million...
11-4 NPV
Your division is considering two projects with the following
cash flows (in millions):
0
1
2
3
Project A
-$11
$4
$7
$1
Project B
-$20
$12
$5
$9
What are the projects' NPVs assuming the WACC is 5%? Round your
answer to two decimal places. Do not round your intermediate
calculations. Enter your answer in millions. For example, an answer
of $10,550,000 should be entered as 10.55. Negative value should be
indicated by a minus sign.
Project...
Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...
Question 6 5 pts (Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4. $2000 $1000 5 $1000 ($1000) What is the approximate crossover point between the two projects if the required rate of return is 9.5%? 12.39% O 7.24% There is no crossover point in this case. 0 7.57% O 6.12% Question 7 5 pts (Numbers in...