Question

Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive project1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar.

2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.

3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar.

Please show all work. Thank you.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

DZ f =SUM(D3:06) B С D E - A 1 Project A 2 year Cash flows 3 0 4 F G H Project A year Cash flows pv@11.84% Present value 0 $

D7 f =SUM(D3:06) B С D E G H A 1 Project A 2 year 3 0 pv@8.5% Project A year 0 1 4 1 1 Cash flows -420000 140000 230000 33100

Add a comment
Know the answer?
Add Answer to:
1. Calculate the net present value (NPV) for both projects, and determine which project should be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its ex...

    11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $36,500 and its expected cash flows would be $8,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. O I. Both Projects S and L, since both projects have IRR's > 0. O II. Project...

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...

    If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...

  • KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value...

    KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value (NPV) c. Internal rate of return (IRR) d. NPV profile; crossover rate e. Mutually exclusive projects; independent projects f. Nonnormal cash flows; normal cash flows; multiple IRRS g. Modified internal rate of return (MIRR) h. Payback period; discounted payback CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected cash flows...

  • (Related to Checkpoint 11.1 and Checkpoint 11,4) (IRR and NPV calculation) The cash flows for three...

    (Related to Checkpoint 11.1 and Checkpoint 11,4) (IRR and NPV calculation) The cash flows for three independent projects are found below: a. Calculate the IRR for each of the projects. b. If the discount rate for all three projects is 11 percent, which project or projects would you want to undertake? c. What is the nel present value of each of the projects where the appropriate discount rate is 11 percent? a. The IRR of Project Ais %. (Round to...

  • 3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should...

    3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...

  • solve using excel Net Present Value and Other Capital Budgeting Measures 6 Consider two mutually exclusive...

    solve using excel Net Present Value and Other Capital Budgeting Measures 6 Consider two mutually exclusive projects with these cash flows: Year Project A -$28,300 13,700 11,600 8,850 4,750 Project B $28,300 3,950 9,450 14,500 16,100 The required rate of return on both projects is 10% a. Which project should be accepted based on the payback period? b. Which project should be accepted based on the PI? c. Which project should be accepted based on the IRR? d. Which project...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • 1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR...

    1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...

  • You are evaluating two mutually exclusive projects. Project 1 has an NPV of $3000 and an...

    You are evaluating two mutually exclusive projects. Project 1 has an NPV of $3000 and an IRR of 15%. Project 2 has expected cash flows of - $22,477 in year 0, $14,236 in year 1, $11,904 in year 2 and $10,013 in year 3. If there is a required rate of 10% on both projects, what is the Net Present Value of Project 2? (Think about but do not answer on line; which project would you choose?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT