Question

You are evaluating two mutually exclusive projects. Project 1 has an NPV of $3000 and an IRR of 15%. Project 2 has expected c

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The cash flows of project 2 are:

Year 0:-22477
Year 1:14236
Year 2:11904
Year 3: 10013

Net present value=-Initial cash outflow + Present value of future cash flows
=-22477+14236/(1+10%)^1+11904/(1+10%)^2+10013/(1+10%)^3
=-22477+12941.81818+9838.016529+7522.915101
=7825.74981

Mutually exclusive projects refers to a set of projects out of which only one project can be seleted.
As the NPV of project 2 is higher than project 1, project 2 should be selected

Add a comment
Know the answer?
Add Answer to:
You are evaluating two mutually exclusive projects. Project 1 has an NPV of $3000 and an...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive...

    (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)

  • If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...

    If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...

  • 8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the...

    8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation (BRC). Both projects require an annual return of 14 percent. Main Page Year Deepwater Fishing New Submarine Ride Incremental (Ride-Fishing) 0 $(850,000.00) $(1,650,000.00) $(800,000.00) 1 $320,000.00 $810,000.00 $490,000.00 2 $470,000.00 $750,000.00 $280,000.00 3 $410,000.00 $690,000.00 $280,000.00 Discount Rate IRR NPV As a financial analyst for BRC, you are asked the following questions: a. If your decision rule is to accept the...

  • need the NPV for both projects Consider the following cash flows on two mutually exclusive projects...

    need the NPV for both projects Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation (BRC). Both projects require an annual return of 16 percent Year 0 Deepwater Fishing -5995,000 415.000 546,000 465.000 New Submarine Ride -$1,940,000 990,000 845 000 840,000 a.1. Compute the IRR for both projects. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, ... 32.16.) IRR Deepwater Fishing Submarine Ride 19.94 % 18.57%...

  • 11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its ex...

    11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $36,500 and its expected cash flows would be $8,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. O I. Both Projects S and L, since both projects have IRR's > 0. O II. Project...

  • You are analyzing two mutually exclusive projects. ​​ NPV ​ IRR Project A​ $10,000​ 18% Project...

    You are analyzing two mutually exclusive projects. ​​ NPV ​ IRR Project A​ $10,000​ 18% Project B​ $18,100​ 13% Which project do you recommend? Defend your answer as to why you recommended the particular project and specifically list what assumptions you used to justify the particular decision. In addition, what other factors should you consider when evaluating the above projects?

  • A firm is considering two mutually exclusive projects with equal lives, Project A has an NPV...

    A firm is considering two mutually exclusive projects with equal lives, Project A has an NPV of $100,000, an IRR of 12%, and a payback period of 3.1 years. Project B has an NPV of $120,000, an IRR of 14%, and a payback period of 2.8 years. The firm should choose________. Question 34 options: 1) Project A because its NPV is higher than Project B's 2) Project A because its payback period is longer than Project B's 3) Project B...

  • As the director of capital budgeting for Denver Corporation, you are evaluating two mutually exclusive projects...

    As the director of capital budgeting for Denver Corporation, you are evaluating two mutually exclusive projects with the following net cash flows. Project X has cash flows of -100,000 in year 0, 50,000 in year 1, 40,000 in year 2, 30,000 in year 3 and 10,000 in year 4. Project Z has cash flows of -100,000 in year 0, 10,000 in year 1, 30,000 in year 2, 40,000 in year 3 and 60,000 in year 4. If Denver's cost of...

  • Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....

    Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,266,858 -$1,100,968 1 256,000 319,000 2 318,000 319,000 3 480,000 319,000 4 483,000 319,000 5 773,000 319,000 NPV of project 1 is$ NPV of project 2 is$ IRR of project 1 is % IRR of project 2 is % Crane Corp should accept:

  • 1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR...

    1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT